Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T19CM04509
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/18/2020 | EXCAVATION/LAYOUT REBAR & ZON | Approved | Approved | |
06/17/2020 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | Inspection canceled by contractor | |
06/03/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PAY STATION APPROVED | |
06/02/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial, Rebar footing And steel plates for Conveyor installed and ok for concrete placement. | |
06/01/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Not Ready | |
05/29/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Not Ready | |
05/20/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial, Completion of Building Footings ok for concrete placement. | |
05/06/2020 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | RVI Cancelled by contractor. Will reschedule | |
05/05/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | RVI FOOTINGS FOR AWNING OK TO POUR |
|
05/04/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | RVI Not ready. Cancelled by contractor. Will reschedule | |
04/15/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial approval For footings between Gridline B and D includes Gridline B footing, but not grid line D footing. Footings on grid line 1,2 and 3 included. |