Permit Details

Status:
Expired
Type:
Residential Building - One or Two Family
Apply Date:
06/19/2019
Applicant:
Description:
SFR LEN400518 T18-M0079

Permit Reviews

Permit Number - T19CM04398
Permit Status: Expired
Permit Description: SFR LEN400518 T18-M0079
Start Date Submittal Complete Date Status  
06/19/2019 RESIDENTIAL - BLDG/ZONING-WALKTHRU 06/21/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T19CM04398
Permit Status: Expired
Permit Description: SFR LEN400518 T18-M0079
Total Outstanding Activity Conditions - 1
Date Name
06/19/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Conditions

Permit Number - T19CM04398
Permit Status: Expired
Permit Description: SFR LEN400518 T18-M0079
Date Description Comments
06/19/2019 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
06/19/2019 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Completed Inspections

Permit Status: Expired
Permit Number: T19CM04398
Permit Description: SFR LEN400518 T18-M0079
Total Completed Inspections - 24
Date Description Inspector Results Comments
08/09/2019 COT - RSPL - Yard Water Line Passed {Activity date: 08/09/2019; Status: Approved; Inspector: AKLEINSORGE; Comment: Entered by DMERANZ1 - Ok to backfill
}
08/09/2019 COT - RSPL - Sewer Passed {Activity date: 08/09/2019; Status: Approved; Inspector: AKLEINSORGE; Comment: Entered by DMERANZ1 - Ok to backfill
}
08/12/2019 COT - RSPL - Rough Soil Passed {Activity date: 08/12/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 08/09/2019; Status: Denied; Inspector: AKLEINSORGE; Comment: Entered by DMERANZ1 - Need all dwv to have water in it, dwv in back left of house did not have any water in it at time of inspection, do not backfill until that section is under test and approved}
08/16/2019 COT - RSBU - Preslab Passed {Activity date: 08/16/2019; Status: Approved; Inspector: AKLEINSORGE; Comment: Entered by DMERANZ1 - Ok for concrete placement
}
08/16/2019 COT - RSEL - Electrical Underground Passed {Activity date: 08/16/2019; Status: Approved; Inspector: AKLEINSORGE; Comment: Entered by DMERANZ1 - }
08/19/2019 COT - RSEL - Grounding/Bonding Passed {Activity date: 08/19/2019; Status: Approved; Inspector: AKLEINSORGE; Comment: Entered by DMERANZ1 - Ufer is installed
} ; {Activity date: 08/16/2019; Status: Denied; Inspector: AKLEINSORGE; Comment: Entered by DMERANZ1 - 1. Missing ufer
}
08/19/2019 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 08/19/2019; Status: Approved; Inspector: AKLEINSORGE; Comment: Entered by DMERANZ1 - All corrections complete, ok for concrete placement
} ; {Activity date: 08/16/2019; Status: Denied; Inspector: AKLEINSORGE; Comment: Entered by DMERANZ1 - 1. Missing hold downs at garage,
2. Interior footings are too small and missing rebar
3. All exterior footings need to be a minimum of 18" deep
}
09/05/2019 COT - RSBU - Roof Nailing Passed {Activity date: 09/05/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - }
09/05/2019 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 09/05/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - }
10/01/2019 PDSD Building Division - TEP PM Clearance Passed {Activity date: 10/01/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by DMERANZ1 - CODE ECO}
10/01/2019 COT - RSEL - Construction Power Passed {Activity date: 10/01/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - (RVI)}
11/15/2019 COT - RSPL - Gas Pressure Test Passed {Activity date: 11/15/2019; Status: Approved; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - }
11/18/2019 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 11/18/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - All corrections have been made, ok to proceed.

} ; {Activity date: 11/15/2019; Status: Denied; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - UFER Not properly attached. Anchor bolts missing at garage opening. Provide minimum clearance from B vent to combustibles. Duct branch fittings and Plenum’s not properly insulated. Duct pinched or compressed through trusses. Provide full radius bends at flex duct, choking at boot boxes not acceptable. Bathtub fitting leaking. Condensate piping penetrating top plate not sealed. Condensate piping draining uphill. Exhaust fans missing out laundry. Inspections stopped at this time this is not a complete list.}
11/18/2019 COT - LCBU - Framing Passed {Activity date: 11/18/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - All corrections have been made, ok to proceed.

} ; {Activity date: 11/15/2019; Status: Denied; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - UFER Not properly attached. Anchor bolts missing at garage opening. Provide minimum clearance from B vent to combustibles. Duct branch fittings and Plenum’s not properly insulated. Duct pinched or compressed through trusses. Provide full radius bends at flex duct, choking at boot boxes not acceptable. Bathtub fitting leaking. Condensate piping penetrating top plate not sealed. Condensate piping draining uphill. Exhaust fans missing out laundry. Inspections stopped at this time this is not a complete list.}
11/18/2019 COT - LCPL - Plumbing Intermediate Passed {Activity date: 11/18/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - All corrections have been made, ok to proceed.

} ; {Activity date: 11/15/2019; Status: Denied; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - UFER Not properly attached. Anchor bolts missing at garage opening. Provide minimum clearance from B vent to combustibles. Duct branch fittings and Plenum’s not properly insulated. Duct pinched or compressed through trusses. Provide full radius bends at flex duct, choking at boot boxes not acceptable. Bathtub fitting leaking. Condensate piping penetrating top plate not sealed. Condensate piping draining uphill. Exhaust fans missing out laundry. Inspections stopped at this time this is not a complete list.}
11/18/2019 RSME - Mechanical Progress Passed {Activity date: 11/18/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - All corrections have been made, ok to proceed.

} ; {Activity date: 11/15/2019; Status: Denied; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - UFER Not properly attached. Anchor bolts missing at garage opening. Provide minimum clearance from B vent to combustibles. Duct branch fittings and Plenum’s not properly insulated. Duct pinched or compressed through trusses. Provide full radius bends at flex duct, choking at boot boxes not acceptable. Bathtub fitting leaking. Condensate piping penetrating top plate not sealed. Condensate piping draining uphill. Exhaust fans missing out laundry. Inspections stopped at this time this is not a complete list.}
12/02/2019 COT - HCBU - Interior Shear Bracing Passed {Activity date: 12/02/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - }
02/10/2020 COT - BULD - SWG Clearance Passed {Activity date: 02/10/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - }
02/18/2020 COT - RSME - Mechanical Final Passed {Activity date: 02/18/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - }
02/18/2020 COT - RSEL - Outdoor Lighting Passed {Activity date: 02/18/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - }
02/18/2020 COT - RSPL - Plumbing Final Passed {Activity date: 02/18/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - }
02/18/2020 RSPL - Plumbing Progress Passed {Activity date: 02/18/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - }
02/18/2020 COT - RSEL - Electrical Final Passed {Activity date: 02/18/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - }
04/09/2020 RSBU - Building Final Passed {Activity date: 04/09/2020; Status: Approved; Inspector: KEN; Comment: Entered by KKARSEN1 - Special Inspection Cert filed} ; {Activity date: 02/18/2020; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - APPROVEDBY INSPECTOR CLOSURE IS PENDING SPECIAL INSPECTION CERTIFICATE FOR POST TENSION SLAB}

Documents

File Name Document Type  
None DOCUMENTS VIEW
None CONSTRPLANS VIEW