Permit Number - T19CM04126
Permit Status: Final
Permit Description: SHELL ONLY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/16/2020 | 3RD PARTY REVIEW - REVISION/OTHER | 01/28/2020 | COMPLETED |
06/10/2019 | PLANS OK TO SUBMIT - COMM | 06/17/2019 | COMPLETED |
06/17/2019 | 3RD PARTY REVIEW - COMMERCIAL | 08/02/2019 | COMPLETED |
08/02/2019 | RESUBMITTAL | 08/05/2019 | COMPLETED |
09/13/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 09/30/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM04126
Permit Status: Final
Permit Description: SHELL ONLY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/10/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM04126
Permit Description: SHELL ONLY
Total Completed Inspections - 44
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/24/2019 | ELECTRIC - UFER | DMUNIZ | Approved | |
10/24/2019 | RESIDENTIAL INTERMEDIATE | DMUNIZ | Approved | |
10/24/2019 | GAS CLEARANCE | DMUNIZ | Approved | |
10/24/2019 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Clear Southwest Gas. |
10/24/2019 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
10/24/2019 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | |
10/24/2019 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | |
10/24/2019 | FRAMING | DMUNIZ | Approved | |
10/31/2019 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | From mechanical yard to mechanical room. |
10/31/2019 | PLUMBING - MD GAS/PRECONST MTG | ESTEVENS | Approved | not complete. |
11/01/2019 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | All DWV's under slab. Two 8" water chiller lines on west side of building. 5' inside and outside of building. |
11/01/2019 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | |
11/13/2019 | BUILDING PRE-SLAB | ESTEVENS | Approved | Entire slab except for 4' pour back at perimeter. |
12/13/2019 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | Tilt up wall panels 15, 16,17,18,19,11,9,8 and 20 |
02/21/2020 | ROOF NAILING | ESTEVENS | Approved | |
04/02/2020 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE ECO |
04/02/2020 | ELECTRIC - CABLE DROP | DMUNIZ | Approved | CLEAR TEP ECO |
04/03/2020 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | RVI Connection to Site Sewer |
04/17/2020 | PLUMBING - ROOF DRAINS | DMUNIZ | Approved | |
04/27/2020 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | RVI supply water under existing driveway, East to west. |
05/12/2020 | SHEET ROCK NAILING | JBURGE | Approved | |
05/12/2020 | STUCCO MESH | JBURGE | Approved | |
05/12/2020 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | |
05/12/2020 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | |
05/14/2020 | PLUMBING - PRE SLAB | ESTEVENS | Approved | |
05/14/2020 | STEM WALL/RETAINING WALL | ESTEVENS | Approved | |
05/14/2020 | FIREWALL/FIREBARRIER/FIRESTOP | ESTEVENS | Approved | |
05/14/2020 | PLUMBING - ABOVE CEILING | ESTEVENS | Approved | |
06/04/2020 | SITE - SEWER | TVALENCIA | Approved | |
06/09/2020 | MECHANICAL - ABOVE CEILING | TVALENCIA | Approved | |
06/09/2020 | ELECTRIC - ABOVE CEILING | TVALENCIA | Approved | |
06/10/2020 | FIRE - FINAL | CBASALDUA | Approved | |
06/10/2020 | FIRE - ALARM FINAL | CBASALDUA | Approved | 1. Will test Fire Alarm with same contractor on T.I. permit. |
06/10/2020 | FIRE INTERMEDIATE | CBASALDUA | Approved | |
06/10/2020 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
06/29/2020 | U VALUE FOR WINDOW | TVALENCIA | Approved | approved |
07/16/2020 | PLUMBING - GAS PRESS TEST FNL | TVALENCIA | Approved | NA 1- Item not applicable. Close permit |
07/16/2020 | ELECTRIC - FINAL | TVALENCIA | Approved | approved |
07/16/2020 | PLUMBING - FINAL | TVALENCIA | Approved | approved |
07/16/2020 | MECHANICAL - FINAL | TVALENCIA | Approved | approved |
07/16/2020 | BUILDING ABOVE CEILING | TVALENCIA | Approved | approved |
07/16/2020 | ELECTRIC - OUTDOOR LIGHTING | TVALENCIA | Approved | approved |
10/08/2020 | ENGINEERING - FINAL | BBENEDON | Approved | |
10/22/2020 | BUILDING - FINAL | TVALENCIA | Approved |