| 10/31/2019 | ELECTRIC - UNDERGROUND | Approved | From mechanical yard to mechanical room. | |
| 10/30/2019 | ELECTRIC - UNDERGROUND | Partial Approval | From electrical room to elevator. | |
| 10/21/2019 | ELECTRIC - UNDERGROUND | Not ready for Inspection | ||
| 10/18/2019 | ELECTRIC - UNDERGROUND | Partial Approval | 3 - 1" from switch gear south to south exterior footing. Secondaries from switch gear east to 20’ east of east foundation. 8 - 3" data conduits to the turn at elevator footing. 1" conduits in data trench to elevator and then continuing south to south footing. All the above are ok to backfill. |