Permit: T19CM04074
Permit Details
Status:
C of o
Type:
MULTI FAMILY NEW
Address:
9300 E VALENCIA RD #12
Address NEW:
9300 E VALENCIA RD #12
Apply Date:
06/06/2019
Applicant:
EGLIN, EVAN SAR
Description:
NEW APARTMENT BUILDING
Architects:
- EGLIN, EVAN SAR
Permit Reviews
Permit Number - T19CM04074
Permit Status: C of o
Permit Description: NEW APARTMENT BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/07/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 06/10/2019 | COMPLETED |
| 06/07/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/16/2019 | COMPLETED |
| 06/09/2020 | REVISION - - 3RD | 08/06/2020 | COMPLETED |
| 07/16/2019 | RESUBMITTAL | 09/16/2019 | COMPLETED |
| 09/16/2019 | REVISION - - 1ST | 09/19/2019 | COMPLETED |
| 10/02/2019 | REVISION - - 2ND | 10/08/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM04074
Permit Status: C of o
Permit Description: NEW APARTMENT BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/06/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM04074
Permit Description: NEW APARTMENT BUILDING
Total Completed Inspections - 34
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/17/2019 | PLUMBING - FINAL | RSHERRY | Approved | WATER DISINFECTION REPORT REQUIRED |
| 09/09/2019 | FIRE SPKLR - FINAL | MRoss | Approved | 1.5" copper riser 200psi tested |
| 09/12/2019 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | OK within building footprint. |
| 03/03/2020 | BUILDING PRE-SLAB | DMUNIZ | Approved | Patios and breezeways ok for concrete placement. |
| 07/10/2020 | EXT METAL CLIPS/EXT SHEATHING | TTREMBULAK | Approved | Approved |
| 07/10/2020 | ROOF NAILING | TTREMBULAK | Approved | Approved |
| 08/25/2020 | FRAMING | DMUNIZ | Approved | Approved |
| 08/25/2020 | BUILDING ABOVE CEILING | DMUNIZ | Approved | Approved |
| 08/25/2020 | STUCCO MESH | DMUNIZ | Approved | Approved |
| 08/25/2020 | U VALUE FOR WINDOW | DMUNIZ | Approved | Approved |
| 08/25/2020 | FIREWALL/FIREBARRIER/FIRESTOP | DMUNIZ | Approved | Approved |
| 08/25/2020 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 08/25/2020 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 08/25/2020 | PLUMBING - ROOF DRAINS | DMUNIZ | Approved | Not Ready, provide water test on roof drains. |
| 08/25/2020 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Partial, Install Traps on condensate lines |
| 11/10/2020 | SHEET ROCK NAILING | WGALLAGHER | Approved | Partial approval for third floor shearwalls |
| 11/10/2020 | BUILDING - PROGRESS | WGALLAGHER | Approved | Not a required inspection |
| 12/23/2020 | TEP CLEARANCE - PM | RCHANDLER | Approved | CODE TMPP/Two services with a total of 25 meters, labeled as follows: House panel, Units 12305, 12107, 12207, 12205, 12307, 12106, 12108, 12205,12308, 12306, 12105, 12208, 12101, 12201, 12303, 12102, 12202, 12304, 12103, 12203, 12301, 12104, 12204, and 12302. |
| 12/24/2020 | ELECTRIC - TEMPORARY SERVICE | RCHANDLER | Approved | 2060 Electric Temporary Power-AP. TMPP clearance for TEP. Two services with a total of 25 meters, labeled as follows: House panel, Units 12305, 12107, 12207, 12205, 12307, 12106, 12108, 12205,12308, 12306, 12105, 12208, 12101, 12201, 12303, 12102, 12202, 12304, 12103, 12203, 12301, 12104, 12204, and 12302. |
| 01/15/2021 | SITE - SEWER | RCHANDLER | Approved | APPROVED |
| 01/15/2021 | PLUMBING - SEWER HCS CONNECT | RCHANDLER | Approved | APPROVED, WAITING FOR PICTURES |
| 01/15/2021 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | APPROVED |
| 02/26/2021 | FIRE - ALARM FINAL | wmotto1 | Approved | |
| 02/26/2021 | FIRE - FINAL | wmotto1 | Approved | |
| 03/11/2021 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | |
| 03/11/2021 | ELECTRIC - PROGRESS | WGALLAGHER | Approved | |
| 03/11/2021 | ELECTRIC - CONSTRUCTION POWER | WGALLAGHER | Approved | |
| 03/11/2021 | ELECTRIC - UNDERGROUND | WGALLAGHER | Approved | |
| 03/12/2021 | ELECTRIC - UFER | WGALLAGHER | Approved | |
| 03/12/2021 | ELECTRIC - FINAL | WGALLAGHER | Approved | |
| 03/12/2021 | MECHANICAL - FINAL | WGALLAGHER | Approved | |
| 08/27/2021 | BUILDING - FINAL | WGALLAGHER | Approved | Approved recommended for C of O |
| 08/27/2021 | EXCAVATION/LAYOUT REBAR & ZON | WGALLAGHER | Approved | 1080 |
| 08/27/2021 | ENGINEERING - FINAL | DROBERTS | Approved | APPROVED PENDING ALL OTHER INSPECTIONS |