Inspection History Details
Inspection Status: Approved
Inspection History: FRAMING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/25/2020 | FRAMING | Approved | Approved | |
| 07/10/2020 | FRAMING | Partial Approval | Partial. Ok for mep’s/ intermediates. | |
| 05/13/2020 | FRAMING | Partial Approval | Partial, Rim Joist’s for third floor decking Inspected ok to proceed. | |
| 04/13/2020 | FRAMING | Partial Approval | RVI 2nd floor deck nailing ok. | |
| 04/10/2020 | FRAMING | Not ready for Inspection | RVI Will reschedule | |
| 04/07/2020 | FRAMING | Not ready for Inspection | RVI-Cancelled by contractor... will reschedule. | |
| 04/02/2020 | FRAMING | Partial Approval | for 1st floor rim boards and beam placement A-35 clips Also shear wall behind electrical panels |
|
| 04/01/2020 | FRAMING | Partial Approval | for 1st floor rim boards and beam placement A-35 clips Also shear wall behind electrical panels |