Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address NEW:
434 E UNIVERSITY BL
Apply Date:
05/17/2019
Applicant:
N/A
Description:
CLINIC
Contractors:
  • TOFEL CONSTRUCTION LLC

Permit Reviews

Permit Number - T19CM03517
Permit Status: C of o
Permit Description: CLINIC
Start Date Submittal Complete Date Status  
05/17/2019 PLANS OK TO SUBMIT - COMM 05/20/2019 COMPLETED Review Details
05/21/2019 COMMERCIAL - TI 06/11/2019 COMPLETED Review Details
06/11/2019 POST 3RD PARTY REVIEW 06/14/2019 ACTIVE Review Details

Outstanding Activity Conditions

Permit Number - T19CM03517
Permit Status: C of o
Permit Description: CLINIC
Total Outstanding Activity Conditions - 1
Date Name
05/17/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T19CM03517
Permit Description: CLINIC
Total Completed Inspections - 20
Date Description Inspector Results Comments
07/15/2019 ELECTRIC - UNDERGROUND RCHANDLER Approved
07/15/2019 PLUMBING - ROUGH, SOIL RCHANDLER Approved
09/04/2019 MECHANICAL - INTERMEDIATE ESTEVENS Approved
09/04/2019 FRAMING ESTEVENS Approved
09/09/2019 PLUMBING - INTERMEDIATE JBURGE Approved
09/13/2019 SHEET ROCK NAILING ESTEVENS Approved Lead lined rock for x-ray room.
10/09/2019 TEP CLEARANCE - AM JBURGE Approved CODE ECO
10/09/2019 ELECTRIC - INTERMEDIATE JBURGE Approved Level #1 TI Electric: transformers, disconnects, power cabinets are all in place.. Ok to energize system. Clearance: Code: ECO
10/16/2019 BUILDING ABOVE CEILING JBURGE Approved Ok to set ceiling tiles.
11/07/2019 EXCAVATION/LAYOUT REBAR & ZON ESTEVENS Approved
11/07/2019 BUILDING PRE-SLAB ESTEVENS Approved
11/13/2019 ELECTRIC - FINAL JBURGE Approved
11/13/2019 SIGN - FINAL BBENEDON Approved
11/27/2019 FIRE SPKLR - FINAL jvincent Approved
11/27/2019 PLUMBING - FINAL JBURGE Approved Bacteria test results have been forwarded to Robert Sherry.
11/27/2019 MECHANICAL - FINAL JBURGE Approved Air balance report has been forwarded to Robert Sherry.
11/27/2019 ENGINEERING - FINAL DROBERT5 Approved THIS INSPECTION IS BEING APPROVED AT THIS TIME WITH THE INTENT THAT THE NON-COMPLIANT ACCESS FROM THIS SITE WILL BE COMPLETED AND MADE COMPLIANT DURING THE PHASE 2 PORTION OF THE SITE ON DP18-0058.
IF THERE ARE ANY QUESTIONS ABOUT THIS SITE YOU CAN CONTACT ME AT (520) 349-7643.
12/06/2019 FIRE - FINAL JPEELDAVIS Approved
12/06/2019 FIRE - ALARM FINAL JPEELDAVIS Approved
12/10/2019 BUILDING - FINAL jburge Approved firre finals completed