Permit: T19CM03265
Permit Details
Apply Date:
05/07/2019
Applicant:
N/A
Description:
MEW MULTI-TENANT SHELL BLDG
Contractors:
- MW MORRISSEY CONSTRUCTION LLC
Permit Reviews
Permit Number - T19CM03265
Permit Status: L of c
Permit Description: MEW MULTI-TENANT SHELL BLDG
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/07/2019 | PLANS OK TO SUBMIT - COMM | 05/14/2019 | COMPLETED |
05/14/2019 | 3RD PARTY REVIEW - COMMERCIAL TI | 07/18/2019 | COMPLETED |
07/18/2019 | POST 3RD PARTY REVIEW | 08/05/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM03265
Permit Status: L of c
Permit Description: MEW MULTI-TENANT SHELL BLDG
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/07/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T19CM03265
Permit Description: MEW MULTI-TENANT SHELL BLDG
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/02/2019 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | Work incomplete at this time. |
08/05/2019 | ELECTRIC - UFER | MHASSAN | Approved | grounding tied into footing. |
08/13/2019 | FIRE - FINAL | gsereno1 | Approved | Underground work was done without permits. Fees will be charged for work without permit. DP plans do not suffice as submission for fire. Plans shall reflect what was seen on inspection, if not new plans shall be submitted or UG shall be changed to resemble plans accordingly. |
08/13/2019 | PLUMBING - YARD WTR LINE/TEST | AKLEINSORGE | Approved | Ok to backfill |
08/13/2019 | PLUMBING - SEWER HCS CONNECT | AKLEINSORGE | Approved | Approval by RChandler on 08/02/19, notes were put under 3005, contractor was doing work before permit was fully approved |
08/13/2019 | SITE - SEWER | AKLEINSORGE | Approved | Approval by RChandler on 08/02/19, notes were put under 3005, contractor was doing work before permit was fully approved |
08/19/2019 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | |
08/19/2019 | PLUMBING - PRE SLAB | MHASSAN | Approved | this approval is really just for the rough soil as this is a shell building pre-slab work should be done with the TI permit. |
08/26/2019 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | Cancelled per phone call with customer. |
08/27/2019 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved | Under building. |
08/27/2019 | BUILDING PRE-SLAB | RCHANDLER | Approved | North side four suites, except East 15 feet. |
09/24/2019 | REINFORCED MASONRY PRE-GROUT | MRAMBER | Approved | Canceled due to weather. |
10/10/2019 | PLUMBING - ROOF DRAINS | TVALENCIA | Approved | 1- Contractor rescheduled for 10/11/19 due on o heavy work load. |
10/11/2019 | ROOF NAILING | DQUINN | Approved | |
10/11/2019 | FRAMING | DQUINN | Approved | |
10/11/2019 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
10/28/2019 | STUCCO MESH | TVALENCIA | Approved | |
10/31/2019 | ELECTRIC - CABLE DROP | ESTEVENS | Approved | |
11/08/2019 | ELECTRIC - OUTDOOR LIGHTING | ESTEVENS | Approved | |
11/25/2019 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
11/25/2019 | ENGINEERING - FINAL | BBENEDON | Approved | Inspection is forTrash enclosure under development package permit. Trash enclosure slab is ready for concrete |
01/29/2020 | PLUMBING - ABOVE CEILING | TVALENCIA | Approved | |
01/29/2020 | PLUMBING - FINAL | TVALENCIA | Approved | |
01/29/2020 | MECHANICAL - INTERMEDIATE | TVALENCIA | Approved | |
01/29/2020 | MECHANICAL - ABOVE CEILING | TVALENCIA | Approved | |
01/29/2020 | MECHANICAL - FINAL | TVALENCIA | Approved | |
01/29/2020 | TEP CLEARANCE - AM | TVALENCIA | Approved | CODE ECO |
02/21/2020 | ELECTRIC - ABOVE CEILING | TVALENCIA | Approved | |
02/21/2020 | FIREWALL/FIREBARRIER/FIRESTOP | TVALENCIA | Approved | |
02/21/2020 | U VALUE FOR WINDOW | TVALENCIA | Approved | |
03/04/2020 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
03/04/2020 | ELECTRIC - FINAL | TVALENCIA | Approved | |
04/03/2020 | FIRE SPKLR - FINAL | jvincent | Approved | video inspection due to covid19. approved/finaled. |
04/08/2020 | FIRE - ALARM FINAL | jvincent | Approved | |
04/09/2020 | BUILDING - FINAL | tvalencia | Approved |