Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 11/25/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
|
| 11/18/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
|
| 11/14/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Two light pole footings on the north west corner. |
| 11/08/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
5 three foot high columns on SW corner and three light poles neat building. |
| 10/24/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
1- (5) Canopy pads okay for concrete. |
| 10/22/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Denied |
Excavation. Denied. Site gate locked. |
| 08/09/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Masonry column footings OK |
| 08/06/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
no new work today, see previous notes. |
| 08/05/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
spread footings for interior steel columns and Masonry spread footings West side of building OK. |