Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
Permit Number - T19CM03265
Inspection Description - REINFORCED MASONRY PRE-GROUT
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/24/2019 | REINFORCED MASONRY PRE-GROUT | Approved | Canceled due to weather. | |
09/23/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | A1 to A2.5 top-out at 20'. From A2.5 to A 2.75 9' to 14' | |
09/20/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 1- Masonry lift 17 feet 4 inches to 21 feet 4 inches from grid line 4 to the 3rd column is okay for grout. 2- Masonry lift 13 feet 4 inches to 17 feet 4 inches from grid line A to the 3rd column is okay for grout. |
|
09/18/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | Grid lines C1 to C4 top out, C4 to B4 top out, C1 to A1 top out. | |
09/16/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | West CMU wall at 9’4"-13’4"; East, North, South walls at 12’-16’. Ok to grout progress areas. | |
09/12/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 1- Masonry steel reinforcement provided and okay to grout the fourth lift to 16 feet between grid line 1 from A to C and from grid line C from 1 to 4 at back of bldg. 15’ 4" and grid line 4 from A to C storefront. | |
09/10/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 1- Steel reinforcement and verticals provided, Okay to grout the walls third lift. 2- Vertical steel provided in columns at front of bldg. are okay for grout |
|
09/09/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | North, south and east walls. 4’ to 8’ | |
09/04/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 1st lift | |
08/09/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | stemwall OK to grout |