Inspection Status: Approved

Inspection History: REINFORCED MASONRY PRE-GROUT

Date Description Inspector Results Comments
09/24/2019 REINFORCED MASONRY PRE-GROUT Approved Canceled due to weather.
09/23/2019 REINFORCED MASONRY PRE-GROUT Partial Approval A1 to A2.5 top-out at 20'. From A2.5 to A 2.75 9' to 14'
09/20/2019 REINFORCED MASONRY PRE-GROUT Partial Approval 1- Masonry lift 17 feet 4 inches to 21 feet 4 inches from grid line 4 to the 3rd column is okay for grout.
2- Masonry lift 13 feet 4 inches to 17 feet 4 inches from grid line A to the 3rd column is okay for grout.
09/18/2019 REINFORCED MASONRY PRE-GROUT Partial Approval Grid lines C1 to C4 top out, C4 to B4 top out, C1 to A1 top out.
09/16/2019 REINFORCED MASONRY PRE-GROUT Partial Approval West CMU wall at 9’4"-13’4"; East, North, South walls at 12’-16’. Ok to grout progress areas.
09/12/2019 REINFORCED MASONRY PRE-GROUT Partial Approval 1- Masonry steel reinforcement provided and okay to grout the fourth lift to 16 feet between grid line 1 from A to C and from grid line C from 1 to 4 at back of bldg. 15’ 4" and grid line 4 from A to C storefront.
09/10/2019 REINFORCED MASONRY PRE-GROUT Partial Approval 1- Steel reinforcement and verticals provided, Okay to grout the walls third lift.
2- Vertical steel provided in columns at front of bldg. are okay for grout
09/09/2019 REINFORCED MASONRY PRE-GROUT Partial Approval North, south and east walls. 4’ to 8’
09/04/2019 REINFORCED MASONRY PRE-GROUT Partial Approval 1st lift
08/09/2019 REINFORCED MASONRY PRE-GROUT Partial Approval stemwall OK to grout