Permit: T19CM01742
Permit Details
Apply Date:
03/12/2019
Applicant:
N/A
Description:
NEW SFR
Contractors:
- SILVA DIVERSIFIED CONSTRUCTION CO LLC
Permit Reviews
Permit Number - T19CM01742
Permit Status: Final
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/12/2019 | PLANS OK TO SUBMIT - RES | 03/12/2019 | COMPLETED |
| 03/12/2019 | RESIDENTIAL - BLDG/WWM | 04/23/2019 | COMPLETED |
| 04/23/2019 | RESUBMITTAL | 04/25/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM01742
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/12/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM01742
Permit Description: NEW SFR
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/03/2019 | ELECTRIC - UFER | RCAMACHO | Approved | |
| 05/06/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | OK to pour footings |
| 05/13/2019 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | |
| 05/24/2019 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | |
| 05/28/2019 | ELECTRIC - UNDERGROUND | BSTEVENS | Approved | |
| 05/28/2019 | BUILDING PRE-SLAB | BSTEVENS | Approved | |
| 07/12/2019 | REINFORCED MASONRY PRE-GROUT | BSTEVENS | Approved | |
| 07/12/2019 | ROOF NAILING | BSTEVENS | Approved | |
| 08/01/2019 | TEP CLEARANCE - PM | MHASSAN | Approved | CODE ECO |
| 08/01/2019 | ELECTRIC - CONSTRUCTION POWER | MHASSAN | Approved | OK to clear electric ECO |
| 08/28/2019 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | |
| 08/28/2019 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | |
| 08/28/2019 | RESIDENTIAL INTERMEDIATE | ESTEVENS | Approved | |
| 09/30/2019 | TEP CLEARANCE - AM | BSTEVENS | Approved | CODE ECO RESEND |
| 10/16/2019 | PLUMBING - SEWER HCS CONNECT | TVALENCIA | Approved | |
| 02/19/2020 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
| 02/19/2020 | PLUMBING - YARD WTR LINE/TEST | TVALENCIA | Approved | |
| 02/19/2020 | PLUMBING - FINAL | TVALENCIA | Approved | |
| 02/19/2020 | MECHANICAL - FINAL | TVALENCIA | Approved | |
| 02/19/2020 | ELECTRIC - FINAL | TVALENCIA | Approved | |
| 02/19/2020 | FRAMING | TVALENCIA | Approved | |
| 02/19/2020 | BUILDING - FINAL | TVALENCIA | Approved |