Permit: T19CM01180
Permit Details
Apply Date:
02/19/2019
Applicant:
BURTON AND ASSOCIATES ARCHITECHETS
Description:
NEW GYMNASIUM
Contractors:
- RIO WEST DEVELOPMENT AND CONSTR *C*
Permit Reviews
Permit Number - T19CM01180
Permit Status: C of o
Permit Description: NEW GYMNASIUM
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/19/2019 | PLANS OK TO SUBMIT - COMM | 02/19/2019 | COMPLETED |
02/19/2019 | COMMERCIAL - NEW | 04/04/2019 | COMPLETED |
04/04/2019 | RESUBMITTAL | 08/23/2019 | COMPLETED |
06/05/2020 | REVISION - - 2ND | 06/05/2020 | COMPLETED |
09/04/2019 | RESUBMITTAL | 09/17/2019 | COMPLETED |
09/18/2019 | RESUBMITTAL | 10/02/2019 | COMPLETED |
10/02/2019 | RESUBMITTAL | 10/15/2019 | COMPLETED |
10/15/2019 | REVISION - - 1ST | 10/16/2019 | COMPLETED |
10/16/2019 | REVISION - - 1ST | 06/05/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM01180
Permit Status: C of o
Permit Description: NEW GYMNASIUM
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/19/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM01180
Permit Description: NEW GYMNASIUM
Total Completed Inspections - 39
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/23/2019 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | Footer at South retaining wall along the building OK |
11/07/2019 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | No work at this time. |
11/07/2019 | PLUMBING - PRE SLAB | MRAMBER | Approved | |
11/07/2019 | ELECTRIC - UFER | MRAMBER | Approved | |
11/07/2019 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | OK within building footprint. |
11/07/2019 | BUILDING PRE-SLAB | MRAMBER | Approved | |
04/28/2020 | ELECTRIC - INTERMEDIATE | TTREMBULAK | Approved | RVI |
05/04/2020 | BUILDING - PROGRESS | TTREMBULAK | Approved | RVI Partial. Framing ok for drywall. |
05/19/2020 | SITE - SEWER | TTREMBULAK | Approved | Approved. Ok to backfill. |
05/19/2020 | PLUMBING - SEWER HCS CONNECT | TTREMBULAK | Approved | |
05/27/2020 | FIRE SPKLR - FINAL | MRoss | Approved | Separate permit for fire service undergorund needed -Visual inspection performed on pipe already installed. |
05/27/2020 | PLUMBING - YARD WTR LINE/TEST | TTREMBULAK | Approved | |
06/03/2020 | TEP CLEARANCE - AM | DMUNIZ | Approved | CODE ECO |
06/03/2020 | ELECTRIC - PROGRESS | DMUNIZ | Approved | Clear TEP ECO |
10/06/2020 | MECHANICAL - ABOVE CEILING | TTREMBULAK | Approved | Approved |
10/06/2020 | PLUMBING - ABOVE CEILING | TTREMBULAK | Approved | Approved |
10/06/2020 | ELECTRIC - ABOVE CEILING | TTREMBULAK | Approved | Approved |
10/06/2020 | BUILDING ABOVE CEILING | TTREMBULAK | Approved | Approved |
11/16/2020 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
11/30/2020 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETE |
01/06/2021 | STEM WALL/RETAINING WALL | TTREMBULAK | Approved | |
01/06/2021 | MECHANICAL - PROGRESS | TTREMBULAK | Approved | |
01/06/2021 | MECHANICAL - INTERMEDIATE | TTREMBULAK | Approved | |
01/06/2021 | PLUMBING - PROGRESS | TTREMBULAK | Approved | |
01/06/2021 | OUTDOOR LIGHTING FINAL | TTREMBULAK | Approved | |
01/06/2021 | ELECTRIC - FINAL | TTREMBULAK | Approved | |
01/06/2021 | ELECTRIC - OUTDOOR LIGHTING | TTREMBULAK | Approved | |
01/06/2021 | ELECTRIC - CONSTRUCTION POWER | TTREMBULAK | Approved | APPROVED |
01/06/2021 | U VALUE FOR WINDOW | TTREMBULAK | Approved | APPROVED |
01/06/2021 | ROOF NAILING | TTREMBULAK | Approved | |
01/06/2021 | EXT METAL CLIPS/EXT SHEATHING | TTREMBULAK | Approved | |
01/15/2021 | FIRE - FINAL | jfordney | Approved | |
01/15/2021 | FIRE - ALARM FINAL | jfordney | Approved | |
02/05/2021 | NPPO - FINAL | DROBERTS | Approved | |
02/05/2021 | SIGN - FINAL | DROBERTS | Approved | |
02/05/2021 | LANDSCAPE - FINAL | DROBERTS | Approved | APPROVED |
02/09/2021 | RIGHT OF WAY - FINAL | BMONG | Approved | NO ISSUES IN THE ROW |
02/11/2021 | BUILDING - FINAL | DROBERTS | Approved | |
02/11/2021 | ENGINEERING - FINAL | DROBERTS | Approved |