Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T19CM01138
Permit Details
Apply Date:
02/15/2019
Applicant:
CARLOS FLORES
Description:
RESTAURANT
Architects:
- CARHUFF, PHILIP ANDREW
Contractors:
- DESERTBUILD CONSTRUCTION LLC
Permit Reviews
Permit Number - T19CM01138
Permit Status: C of o
Permit Description: RESTAURANT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/15/2019 | COMMERCIAL - NEW | 02/19/2019 | COMPLETED |
02/19/2019 | COMMERCIAL - NEW | 03/28/2019 | COMPLETED |
04/02/2019 | RESUBMITTAL | 04/04/2019 | COMPLETED |
04/04/2019 | RESUBMITTAL | 04/26/2019 | COMPLETED |
04/26/2019 | RESUBMITTAL | 05/01/2019 | COMPLETED |
08/02/2019 | REVISION - - 1ST | 08/02/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM01138
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/15/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM01138
Permit Description: RESTAURANT
Total Completed Inspections - 44
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/28/2019 | ELECTRIC - UFER | MHASSAN | Approved | |
05/31/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | stem walls OK |
06/18/2019 | BUILDING PRE-SLAB | MHASSAN | Approved | |
06/20/2019 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
07/15/2019 | PLUMBING - SEWER HCS CONNECT | MHASSAN | Approved | |
07/15/2019 | ROOF NAILING | MHASSAN | Approved | |
07/18/2019 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | |
08/01/2019 | BUILDING - PROGRESS | TVALENCIA | Approved | 1- Electric metal boxes and MC cables in walls are okay to cover. 2- DWV system and in wall domestic water distribution Okay to cover. |
08/09/2019 | STUCCO MESH | TVALENCIA | Approved | |
08/27/2019 | TEP CLEARANCE - PM | MHASSAN | Approved | CODE ECO |
08/27/2019 | ELECTRIC - TEMPORARY SERVICE | MHASSAN | Approved | OK to clear electric ECO |
10/01/2019 | MECHANICAL - ABOVE CEILING | TVALENCIA | Approved | |
10/01/2019 | ELECTRIC - ABOVE CEILING | TVALENCIA | Approved | |
10/08/2019 | GAS CLEARANCE | TVALENCIA | Approved | |
10/08/2019 | PLUMBING - GAS PRESSURE TEST | TVALENCIA | Approved | Clear gas meter |
10/21/2019 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
10/21/2019 | ELECTRIC - FINAL | TVALENCIA | Approved | |
10/23/2019 | FIRE - KITCHEN EXH HOOD FINAL | JPEELDAVIS | Approved | |
10/24/2019 | HEALTH DEPT - FINAL 724-7908 | JKINCAID | Approved | |
10/25/2019 | MECHANICAL - INTERMEDIATE | TVALENCIA | Approved | |
10/25/2019 | MECHANICAL - HOODS | TVALENCIA | Approved | |
10/25/2019 | PLUMBING - YARD WTR LINE/TEST | TVALENCIA | Approved | |
10/25/2019 | PLUMBING - ROOF DRAINS | TVALENCIA | Approved | |
10/25/2019 | PLUMBING - INTERMEDIATE | TVALENCIA | Approved | |
10/25/2019 | PLUMBING - BACK WATER VALVE | TVALENCIA | Approved | |
10/25/2019 | SITE - SEWER | TVALENCIA | Approved | |
10/25/2019 | ELECTRIC - OUTDOOR LIGHTING | TVALENCIA | Approved | |
10/25/2019 | ELECTRIC - PROGRESS | TVALENCIA | Approved | |
10/25/2019 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | |
10/25/2019 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | |
10/25/2019 | ELECTRIC - INTERMEDIATE | TVALENCIA | Approved | |
10/25/2019 | CERTIFICATE OF OCCUPANCY | TVALENCIA | Approved | |
10/25/2019 | REINFORCED MASONRY PRE-GROUT | TVALENCIA | Approved | |
10/25/2019 | BUILDING ABOVE CEILING | TVALENCIA | Approved | |
10/25/2019 | FRAMING | TVALENCIA | Approved | |
10/25/2019 | U VALUE FOR WINDOW | TVALENCIA | Approved | |
10/30/2019 | ENGINEERING - FINAL | BBENEDON | Approved | |
10/30/2019 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
10/31/2019 | FIRE - FINAL | jvincent | Approved | |
10/31/2019 | FIRE - FINAL | jvincent | Approved | obtain POA operational permit |
10/31/2019 | FIRE - ALARM FINAL | jvincent | Approved | |
10/31/2019 | FIRE SPKLR - FINAL | jvincent | Approved | |
11/15/2019 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
11/18/2019 | BUILDING - FINAL | TVALENCIA | Approved |