Permit: T19CM00152
Permit Details
Apply Date:
01/09/2019
Applicant:
N/A
Description:
NEW SHELL RETAIL
Contractors:
- CALDWELL CONSTRUCTION LLC
Permit Reviews
Permit Number - T19CM00152
Permit Status: L of c
Permit Description: NEW SHELL RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/09/2019 | PLANS OK TO SUBMIT - COMM | 01/11/2019 | COMPLETED |
| 01/11/2019 | COMMERCIAL - NEW | 02/08/2019 | COMPLETED |
| 02/11/2019 | RESUBMITTAL | 05/17/2019 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T19CM00152
Permit Status: L of c
Permit Description: NEW SHELL RETAIL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/09/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T19CM00152
Permit Description: NEW SHELL RETAIL
Total Completed Inspections - 33
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/20/2019 | ELECTRIC - UFER | DMUNIZ | Approved | 3/0CU conductor bonded to Rebar in 3 Locations for Fire Riser, Gas, & Switchgear. |
| 10/23/2019 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | 4-4" Secondary Conduits from Transformer to location of New service ok to backfill. |
| 10/29/2019 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | Stem walls for Exterior Columns ok for concrete placement. |
| 11/01/2019 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | |
| 12/03/2019 | PLUMBING - BACK WATER VALVE | DMUNIZ | Approved | |
| 12/03/2019 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | |
| 12/03/2019 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | Connection from Grease Interceptor and Sanitary waste lines to 2way Clean outs with backwater valve to Manhole ok to backfill. |
| 12/09/2019 | SITE - SEWER | DMUNIZ | Approved | |
| 12/09/2019 | FRAMING | DMUNIZ | Approved | |
| 12/11/2019 | ROOF NAILING | DMUNIZ | Approved | |
| 12/11/2019 | PLUMBING - ROOF DRAINS | DMUNIZ | Approved | |
| 12/13/2019 | GAS CLEARANCE | DMUNIZ | Approved | |
| 12/13/2019 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Ok Clearance SWG |
| 12/17/2019 | PLUMBING - INTERMEDIATE | WGALLAG1 | Approved | |
| 12/18/2019 | EXT METAL CLIPS/EXT SHEATHING | DMUNIZ | Approved | Sheathing on Exterior shell ok to start lath. |
| 12/20/2019 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | |
| 12/20/2019 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | |
| 12/20/2019 | ELECTRIC - TEMPORARY SERVICE | DMUNIZ | Approved | |
| 01/07/2020 | ELECTRIC - ABOVE CEILING | WGALLAG1 | Approved | no ceiling to be installed on this permit |
| 01/07/2020 | STUCCO MESH | WGALLAG1 | Approved | EFIS waterproof complete |
| 01/10/2020 | REINFORCED MASONRY PRE-GROUT | WGALLAG1 | Approved | |
| 01/22/2020 | TEP CLEARANCE - PM | DMUNIZ | Approved | House Panel, Suite #100, 110, 120, 130 CODE ECO |
| 02/12/2020 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
| 03/13/2020 | MECHANICAL - FINAL | WGALLAGHER | Approved | |
| 03/13/2020 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | |
| 03/13/2020 | ELECTRIC - FINAL | WGALLAGHER | Approved | |
| 03/13/2020 | ELECTRIC - OUTDOOR LIGHTING | WGALLAGHER | Approved | |
| 03/16/2020 | FIRE - FINAL | CBASALDUA | Approved | |
| 03/16/2020 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 03/16/2020 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 03/24/2020 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 03/27/2020 | BUILDING - FINAL | RSHERRY | Approved | |
| 03/27/2020 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |