Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 10/29/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
Stem walls for Exterior Columns ok for concrete placement. |
| 10/14/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Exterior Stem walls of shell for Unit #2 & #3 ok for concrete placement. |
| 10/04/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
concrete placement for stem wall surrounds for MOD Pizza ok for concrete placement. |
| 09/27/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Footings for Exterior stem walls for future columns Northside of GL 4.0 ok for concrete placement. |
| 09/23/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Exterior column footings ok for concrete placement. |
| 09/20/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Exterior footers from GL 1-4 ok for concrete placement |