Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
3920 E GRANT RD
Address NEW:
3920 E GRANT RD
Apply Date:
12/28/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
FITNESS CENTER
Architects:
  • GARCIA DAVID V
Contractors:
  • CALIENTE CONSTRUCTION INC , ***APA***

Permit Reviews

Permit Number - T18CM10049
Permit Status: C of o
Permit Description: FITNESS CENTER
Start Date Submittal Complete Date Status  
01/08/2019 3RD PARTY REVIEW - COMMERCIAL 02/07/2019 COMPLETED Review Details
02/07/2019 OTHER 03/11/2019 COMPLETED Review Details
04/04/2019 3RD PARTY REVIEW - REVISION/OTHER 05/21/2019 COMPLETED Review Details
05/21/2019 3RD PARTY REVIEW - REVISION/OTHER 05/21/2019 COMPLETED Review Details
05/21/2019 POST 3RD PARTY REVIEW 07/11/2019 COMPLETED Review Details
10/01/2019 REVISION - - 1ST 10/01/2019 COMPLETED Review Details
12/28/2018 PLANS OK TO SUBMIT - COMM 01/03/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM10049
Permit Status: C of o
Permit Description: FITNESS CENTER
Total Outstanding Activity Conditions - 1
Date Name
12/28/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T18CM10049
Permit Description: FITNESS CENTER
Total Completed Inspections - 40
Date Description Inspector Results Comments
05/10/2019 ELECTRIC - UFER BSTEVENS Approved
05/16/2019 STEM WALL/RETAINING WALL MRAMBER Approved
05/22/2019 REINFORCED MASONRY PRE-GROUT RCHANDLER Approved Fill in window/doors three openings.
05/31/2019 PLUMBING - GAS PRESSURE TEST RCHANDLER Approved
06/07/2019 PLUMBING - INTERMEDIATE ESTEVENS Approved Employee lounge, both kids care restrooms and fountain by basketball court.
07/10/2019 ROOF NAILING RCHANDLER Approved Looked at facade roof.
07/15/2019 TEP CLEARANCE - PM MRAMBER Approved METERS 1&2 CODE INCR
07/15/2019 ELECTRIC - SERVICE UPGRADE MRAMBER Approved INCR OK to clear, transformer, meters one and two OK.
08/28/2019 PLUMBING - ROUGH, SOIL DQUINN Approved Perimeter deck drain rough ok to backfill
09/04/2019 PLUMBING - PRE SLAB RCHANDLER Approved
09/12/2019 MECHANICAL - INTERMEDIATE RCHANDLER Approved
09/12/2019 ELECTRIC - OUTDOOR LIGHTING RCHANDLER Approved
09/12/2019 ELECTRIC - INTERMEDIATE RCHANDLER Approved
09/12/2019 ELECTRIC - UNDERGROUND RCHANDLER Approved
09/12/2019 SHEET ROCK NAILING RCHANDLER Approved
09/12/2019 FIREWALL/FIREBARRIER/FIRESTOP RCHANDLER Approved
09/12/2019 EXT METAL CLIPS/EXT SHEATHING RCHANDLER Approved
09/12/2019 BUILDING PRE-SLAB RCHANDLER Approved
09/12/2019 EXCAVATION/LAYOUT REBAR & ZON RCHANDLER Approved
09/12/2019 MECHANICAL - ABOVE CEILING RCHANDLER Approved
09/12/2019 FRAMING RCHANDLER Approved
09/25/2019 FIRE SPKLR - FINAL jvincent Approved
09/26/2019 ELECTRIC - ABOVE CEILING RCHANDLER Approved
09/27/2019 NPPO - FINAL RLEDONNE Approved
09/27/2019 SIGN - FINAL RLEDONNE Approved
09/27/2019 LANDSCAPE - FINAL RLEDONNE Approved
09/27/2019 RIGHT OF WAY - FINAL DR Approved NO ROW IMPACT
10/04/2019 GAS CLEARANCE RCHANDLER Approved
10/04/2019 PLUMBING - GAS PRESS TEST FNL RCHANDLER Approved Clearance SWG. OK to connect.
10/16/2019 PLUMBING - FINAL RCHANDLER Approved chlorination report approved and sent to records
10/25/2019 FIRE - FINAL jvincent Approved
10/25/2019 FIRE - FINAL jvincent Approved only waiting on annual sprink insp report
10/25/2019 FIRE - ALARM FINAL jvincent Approved
10/25/2019 PLUMBING - ABOVE CEILING RCHANDLER Approved
10/25/2019 OUTDOOR LIGHTING FINAL RCHANDLER Approved
10/25/2019 ELECTRIC - FINAL RCHANDLER Approved
10/25/2019 BUILDING ABOVE CEILING RCHANDLER Approved
10/25/2019 ENGINEERING - FINAL RLEDONNE Approved
11/13/2019 BUILDING - FINAL RSHERRY Approved
11/13/2019 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT COMPLETED