Permit: T18CM10049
Permit Details
Apply Date:
12/28/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
FITNESS CENTER
Architects:
- GARCIA DAVID V
Contractors:
- CALIENTE CONSTRUCTION INC , ***APA***
Permit Reviews
Permit Number - T18CM10049
Permit Status: C of o
Permit Description: FITNESS CENTER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/08/2019 | 3RD PARTY REVIEW - COMMERCIAL | 02/07/2019 | COMPLETED |
| 02/07/2019 | OTHER | 03/11/2019 | COMPLETED |
| 04/04/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 05/21/2019 | COMPLETED |
| 05/21/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 05/21/2019 | COMPLETED |
| 05/21/2019 | POST 3RD PARTY REVIEW | 07/11/2019 | COMPLETED |
| 10/01/2019 | REVISION - - 1ST | 10/01/2019 | COMPLETED |
| 12/28/2018 | PLANS OK TO SUBMIT - COMM | 01/03/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM10049
Permit Status: C of o
Permit Description: FITNESS CENTER
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/28/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM10049
Permit Description: FITNESS CENTER
Total Completed Inspections - 40
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/10/2019 | ELECTRIC - UFER | BSTEVENS | Approved | |
| 05/16/2019 | STEM WALL/RETAINING WALL | MRAMBER | Approved | |
| 05/22/2019 | REINFORCED MASONRY PRE-GROUT | RCHANDLER | Approved | Fill in window/doors three openings. |
| 05/31/2019 | PLUMBING - GAS PRESSURE TEST | RCHANDLER | Approved | |
| 06/07/2019 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | Employee lounge, both kids care restrooms and fountain by basketball court. |
| 07/10/2019 | ROOF NAILING | RCHANDLER | Approved | Looked at facade roof. |
| 07/15/2019 | TEP CLEARANCE - PM | MRAMBER | Approved | METERS 1&2 CODE INCR |
| 07/15/2019 | ELECTRIC - SERVICE UPGRADE | MRAMBER | Approved | INCR OK to clear, transformer, meters one and two OK. |
| 08/28/2019 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | Perimeter deck drain rough ok to backfill |
| 09/04/2019 | PLUMBING - PRE SLAB | RCHANDLER | Approved | |
| 09/12/2019 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | |
| 09/12/2019 | ELECTRIC - OUTDOOR LIGHTING | RCHANDLER | Approved | |
| 09/12/2019 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | |
| 09/12/2019 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved | |
| 09/12/2019 | SHEET ROCK NAILING | RCHANDLER | Approved | |
| 09/12/2019 | FIREWALL/FIREBARRIER/FIRESTOP | RCHANDLER | Approved | |
| 09/12/2019 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | |
| 09/12/2019 | BUILDING PRE-SLAB | RCHANDLER | Approved | |
| 09/12/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | |
| 09/12/2019 | MECHANICAL - ABOVE CEILING | RCHANDLER | Approved | |
| 09/12/2019 | FRAMING | RCHANDLER | Approved | |
| 09/25/2019 | FIRE SPKLR - FINAL | jvincent | Approved | |
| 09/26/2019 | ELECTRIC - ABOVE CEILING | RCHANDLER | Approved | |
| 09/27/2019 | NPPO - FINAL | RLEDONNE | Approved | |
| 09/27/2019 | SIGN - FINAL | RLEDONNE | Approved | |
| 09/27/2019 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 09/27/2019 | RIGHT OF WAY - FINAL | DR | Approved | NO ROW IMPACT |
| 10/04/2019 | GAS CLEARANCE | RCHANDLER | Approved | |
| 10/04/2019 | PLUMBING - GAS PRESS TEST FNL | RCHANDLER | Approved | Clearance SWG. OK to connect. |
| 10/16/2019 | PLUMBING - FINAL | RCHANDLER | Approved | chlorination report approved and sent to records |
| 10/25/2019 | FIRE - FINAL | jvincent | Approved | |
| 10/25/2019 | FIRE - FINAL | jvincent | Approved | only waiting on annual sprink insp report |
| 10/25/2019 | FIRE - ALARM FINAL | jvincent | Approved | |
| 10/25/2019 | PLUMBING - ABOVE CEILING | RCHANDLER | Approved | |
| 10/25/2019 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | |
| 10/25/2019 | ELECTRIC - FINAL | RCHANDLER | Approved | |
| 10/25/2019 | BUILDING ABOVE CEILING | RCHANDLER | Approved | |
| 10/25/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 11/13/2019 | BUILDING - FINAL | RSHERRY | Approved | |
| 11/13/2019 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |