Permit: T18CM09841
Permit Details
Apply Date:
12/18/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW MULTI -TENANT SHELL BLDG.
Contractors:
- DIVISION II CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T18CM09841
Permit Status: Final
Permit Description: NEW MULTI -TENANT SHELL BLDG.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/31/2019 | RESUBMITTAL | 04/04/2019 | COMPLETED |
| 04/04/2019 | RESUBMITTAL - TI ALL | 05/03/2019 | COMPLETED |
| 05/03/2019 | RESUBMITTAL | 05/10/2019 | COMPLETED |
| 06/06/2019 | REVISION - - 1ST | 06/11/2019 | COMPLETED |
| 06/11/2019 | REVISION - - 1ST | 08/01/2019 | COMPLETED |
| 08/01/2019 | REVISION - - 2ND | 08/06/2019 | COMPLETED |
| 12/18/2018 | COMMERCIAL - NEW | 12/19/2018 | COMPLETED |
| 12/19/2018 | COMMERCIAL - NEW | 01/31/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM09841
Permit Status: Final
Permit Description: NEW MULTI -TENANT SHELL BLDG.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/18/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM09841
Permit Description: NEW MULTI -TENANT SHELL BLDG.
Total Completed Inspections - 38
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/20/2019 | PLUMBING - FINAL | RSHERRY | Approved | WATER DISINFECTION REPORT REQUIRED |
| 08/07/2019 | STEM WALL/RETAINING WALL | DQUINN | Approved | All stems for south building ok to pour. |
| 08/22/2019 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 09/06/2019 | ELECTRIC - UFER | DQUINN | Approved | |
| 09/06/2019 | BUILDING PRE-SLAB | DQUINN | Approved | West, north and east footings, and slabs 1 3 ok to pour. Wraps ok |
| 10/09/2019 | SITE - SEWER | DQUINN | Approved | Last run of main drain lines, from grease traps to hcs, ok to backfill. |
| 10/09/2019 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | Last run of main drain lines, from grease traps to hcs, ok to backfill. |
| 10/22/2019 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | Rough for postinos , connected to main drain line on west side, ok to backfill. This inspection is being noted on this permit as they wait for postino’s permit from cot |
| 10/24/2019 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | Potables from meters to all units ok to backfill |
| 11/25/2019 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Light pole footings and underground conduits ok to pour and backfill. |
| 11/25/2019 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
| 11/29/2019 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE ECO |
| 11/29/2019 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | The TEP clearance code is ECO. |
| 11/29/2019 | ELECTRIC - TEMPORARY SERVICE | ESTEVENS | Approved | The TEP clearance code is ECO. |
| 12/02/2019 | STUCCO MESH | JCLAXTON | Approved | Ok to proceed |
| 12/02/2019 | ROOF NAILING | JCLAXTON | Approved | Ok to proceed |
| 12/11/2019 | FRAMING | JCLAXTON | Approved | This is for the 3 demising walls only. |
| 12/13/2019 | PLUMBING - ROOF DRAINS | DQUINN | Approved | |
| 12/20/2019 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | Cancelled due to leaks |
| 12/20/2019 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | |
| 12/20/2019 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | |
| 12/20/2019 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | |
| 12/27/2019 | BUILDING - PROGRESS | RCHANDLER | Approved | Nailing of soffit sheathing. |
| 01/30/2020 | MECHANICAL - FINAL | ESTEVENS | Approved | |
| 02/06/2020 | U VALUE FOR WINDOW | DQUINN | Approved | |
| 02/06/2020 | BUILDING ABOVE CEILING | DQUINN | Approved | |
| 02/06/2020 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | AP PER 2090 AP |
| 02/06/2020 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved | AP PER 2090 AP |
| 02/06/2020 | ELECTRIC - PROGRESS | DQUINN | Approved | AP PER 2090 AP |
| 02/06/2020 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | AP PER 2090 AP |
| 02/06/2020 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | AP PER 3090 AP |
| 02/06/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | AP PER 4090 AP |
| 02/06/2020 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
| 02/06/2020 | ELECTRIC - FINAL | DQUINN | Approved | |
| 02/07/2020 | FIRE - FINAL | jvincen1 | Approved | shell only |
| 02/07/2020 | FIRE - ALARM FINAL | jvincen1 | Approved | |
| 02/18/2020 | BUILDING - FINAL | DROBERTS | Approved | |
| 02/18/2020 | ENGINEERING - FINAL | DROBERTS | Approved |