Permit: T18CM08835
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
2030 N CAMINO SERNA
Address NEW:
2030 N CAMINO SERNA
Apply Date:
11/06/2018
Applicant:
SHERREE MONGELLI - VENTURE WEST CONSTRUCTION L L C
Description:
SALON
Contractors:
- VENTURE WEST CONSTRUCTION L L C
- VENTURE WEST INC ***APA
Permit Reviews
Permit Number - T18CM08835
Permit Status: C of o
Permit Description: SALON
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/10/2019 | RESUBMITTAL - TI ALL | 05/08/2019 | COMPLETED |
| 06/10/2019 | RESUBMITTAL | 06/20/2019 | COMPLETED |
| 06/20/2019 | RESUBMITTAL | 06/20/2019 | COMPLETED |
| 11/06/2018 | PLANS OK TO SUBMIT - COMM | 11/06/2018 | COMPLETED |
| 11/06/2018 | COMMERCIAL - TI | 04/10/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM08835
Permit Status: C of o
Permit Description: SALON
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/06/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM08835
Permit Description: SALON
Total Completed Inspections - 36
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/24/2019 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | |
| 08/22/2019 | BUILDING - PROGRESS | RCHANDLER | Approved | Looked at wall sections at back-to-back mini coils are located to allow covering second side with drywall. |
| 08/30/2019 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 08/30/2019 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 08/30/2019 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 08/30/2019 | FRAMING | DQUINN | Approved | |
| 10/02/2019 | BUILDING PRE-SLAB | RCHANDLER | Approved | |
| 10/02/2019 | STEM WALL/RETAINING WALL | RCHANDLER | Approved | |
| 10/02/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | |
| 11/14/2019 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | |
| 11/14/2019 | ELECTRIC - PROGRESS | RCHANDLER | Approved | |
| 11/14/2019 | ELECTRIC - OUTDOOR LIGHTING | RCHANDLER | Approved | |
| 11/14/2019 | FIREWALL/FIREBARRIER/FIRESTOP | RCHANDLER | Approved | |
| 11/14/2019 | BUILDING ABOVE CEILING | RCHANDLER | Approved | |
| 11/14/2019 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | |
| 11/14/2019 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | |
| 11/14/2019 | PLUMBING - ABOVE CEILING | RCHANDLER | Approved | |
| 11/14/2019 | ELECTRIC - SERVICE UPGRADE | RCHANDLER | Approved | |
| 11/14/2019 | ELECTRIC - TEMPORARY SERVICE | RCHANDLER | Approved | |
| 11/14/2019 | ELECTRIC - CONSTRUCTION POWER | RCHANDLER | Approved | |
| 11/14/2019 | ELECTRIC - ABOVE CEILING | RCHANDLER | Approved | |
| 11/14/2019 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved | |
| 11/14/2019 | ELECTRIC - UFER | RCHANDLER | Approved | |
| 11/14/2019 | ROOF NAILING | RCHANDLER | Approved | |
| 11/18/2019 | ELECTRIC - FINAL | RCHANDLER | Approved | |
| 11/18/2019 | PLUMBING - GAS PRESSURE TEST | RCHANDLER | Approved | |
| 11/20/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | No work outside of building on approve plan. |
| 11/20/2019 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 11/20/2019 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
| 11/21/2019 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | T19FC00981 Cintas for monitoring approved T19FC00937 Favara's for the fire alarm PA need to re-verify the new flow switch |
| 11/21/2019 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | |
| 12/17/2019 | CERTIFICATE OF OCCUPANCY | RCHANDLER | Approved | |
| 12/17/2019 | BUILDING - FINAL | RCHANDLER | Approved | |
| 12/17/2019 | FIRE - FINAL | gsereno1 | Approved | |
| 12/17/2019 | CERTIFICATE OF OCCUPANCY | RCHANDLER | Approved | Building inspections complete, awaiting full fire inspection approval; see previous results. |
| 12/17/2019 | BUILDING - FINAL | RCHANDLER | Approved | Building inspections complete, awaiting full fire inspection approval; see previous results. |