Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T18CM08177
Permit Details
Apply Date:
10/12/2018
Applicant:
MAHER, JOSEPH SAID JR
Description:
NEW INDUSTRIAL BLDG
Architects:
- MAHER, JOSEPH SAID JR
Contractors:
- BARKER CONTRACTING INC **APA**
Permit Reviews
Permit Number - T18CM08177
Permit Status: C of o
Permit Description: NEW INDUSTRIAL BLDG
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/04/2019 | POST 3RD PARTY REVIEW | 02/12/2019 | COMPLETED |
05/29/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 05/29/2019 | COMPLETED |
05/29/2019 | POST 3RD PARTY REVIEW | 05/29/2019 | COMPLETED |
10/12/2018 | PLANS OK TO SUBMIT - COMM | 10/12/2018 | COMPLETED |
10/12/2018 | 3RD PARTY REVIEW - COMMERCIAL TI | 12/19/2018 | COMPLETED |
12/19/2018 | POST 3RD PARTY REVIEW | 02/04/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM08177
Permit Status: C of o
Permit Description: NEW INDUSTRIAL BLDG
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/12/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM08177
Permit Description: NEW INDUSTRIAL BLDG
Total Completed Inspections - 32
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/09/2019 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | Plumbing under slab ok |
04/09/2019 | ELECTRIC - UFER | DMUNIZ | Approved | |
04/10/2019 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | |
05/01/2019 | BUILDING PRE-SLAB | DMUNIZ | Approved | |
06/05/2019 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | Yard water line and tracer ok, Pressure test Approved. |
07/17/2019 | SHEET ROCK NAILING | DMUNIZ | Approved | Riser room & Restroom ok to tape & texture. |
07/17/2019 | FIREWALL/FIREBARRIER/FIRESTOP | DMUNIZ | Approved | Fire assembly on demising wall Approved. |
07/17/2019 | FRAMING | DMUNIZ | Approved | |
09/05/2019 | TEP CLEARANCE - PM | DMUNIZ | Approved | BUILDING #2 & #3 CODE ECO |
09/05/2019 | ROOF NAILING | DMUNIZ | Approved | |
09/05/2019 | REINFORCED MASONRY PRE-GROUT | DMUNIZ | Approved | |
09/05/2019 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | |
09/05/2019 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | |
09/05/2019 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | |
09/05/2019 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Clear TEP (ECO) 2000AMP 277/480V SES for Building #2 & Building #3 ok to energize. |
11/06/2019 | ELECTRIC - FINAL | DMUNIZ | Approved | |
11/06/2019 | PLUMBING - FINAL | DMUNIZ | Approved | Clear Southwest Gas. |
11/06/2019 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
11/06/2019 | MECHANICAL - FINAL | DMUNIZ | Approved | |
11/06/2019 | BUILDING - PROGRESS | DMUNIZ | Approved | |
12/11/2019 | BUILDING - FINAL | DMERANZ1 | Approved | |
12/11/2019 | CERTIFICATE OF OCCUPANCY | DMERANZ1 | Approved | |
12/11/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | |
12/11/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | |
12/11/2019 | FIRE - FINAL | MRoss | Approved | -Provide FDC Knox locking caps on FDCs on all buildings |
12/11/2019 | FIRE - ALARM FINAL | MRoss | Approved | |
12/11/2019 | FIRE SPKLR - FINAL | MRoss | Approved | |
12/11/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | Need to talk to John Van Winkle about notes on approved plans. |
12/11/2019 | GAS CLEARANCE | DMUNIZ | Approved | RESEND |
12/11/2019 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Change order for Gas Line, had to retest please Clear Southwest Gas. |
12/11/2019 | BUILDING - FINAL | DMUNIZ | Approved | APPROVED BY INSPECTOR, Special inspection reports Submitted and Approved, and Water report completed. Ok to Final permit pending Fire and Engineering results. |
12/11/2019 | CERTIFICATE OF OCCUPANCY | DMUNIZ | Approved | Special inspection reports Submitted and Approved, and Water report completed. Ok to Final permit pending Fire and Engineering results. |