Permit: T18CM08172
Permit Details
Apply Date:
10/12/2018
Applicant:
BARBARA JOSLIN
Description:
WAREHOUSE
Contractors:
- CATAMOUNT CONSTRUCTORS INC ***APA***
Permit Reviews
Permit Number - T18CM08172
Permit Status: C of o
Permit Description: WAREHOUSE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/14/2019 | REVISION - - 1ST | 02/25/2019 | COMPLETED |
02/27/2019 | REVISION - - 2ND | 02/27/2019 | COMPLETED |
02/27/2019 | REVISION - - 2ND | 04/30/2019 | COMPLETED |
04/30/2019 | REVISION - - 2ND | 05/07/2019 | COMPLETED |
05/07/2019 | RESUBMITTAL | 05/09/2019 | COMPLETED |
10/12/2018 | PLANS OK TO SUBMIT - COMM | 10/12/2018 | COMPLETED |
10/12/2018 | COMMERCIAL - NEW | 11/19/2018 | COMPLETED |
11/19/2018 | RESUBMITTAL | 12/13/2018 | COMPLETED |
12/13/2018 | RESUBMITTAL | 12/17/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM08172
Permit Status: C of o
Permit Description: WAREHOUSE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/12/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM08172
Permit Description: WAREHOUSE
Total Completed Inspections - 38
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/07/2018 | ENGINEERING - FINAL | JV | Approved | PROVIDE LOT COMBINATION AND EASEMENT RECORDATION DOCUMENTS PRIOR TO ENGINEERING FINAL |
12/13/2018 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
12/13/2018 | PLUMBING - FINAL | RSHERRY | Approved | WATER DISINFECTION REPORT REQUIRED |
12/18/2018 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | Underlab |
12/18/2018 | BUILDING PRE-SLAB | RCHANDLER | Approved | Middle third. |
12/18/2018 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | Work incomplete. |
12/31/2018 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | Found no plumbing under test |
01/03/2019 | ELECTRIC - UFER | MHASSAN | Approved | |
03/19/2019 | STEM WALL/RETAINING WALL | MHASSAN | Approved | |
03/21/2019 | SITE - SEWER | MHASSAN | Approved | |
03/28/2019 | FRAMING | MHASSAN | Approved | |
04/03/2019 | REINFORCED MASONRY PRE-GROUT | MHASSAN | Approved | final approval is for dumpster enclosure. |
05/08/2019 | BUILDING - PROGRESS | MHASSAN | Approved | this was a meeting with the super to walk the job and clean up the open inspections on the permit |
05/08/2019 | PLUMBING - SEWER HCS CONNECT | MHASSAN | Approved | |
05/08/2019 | ELECTRIC - CONSTRUCTION POWER | MHASSAN | Approved | |
05/08/2019 | ELECTRIC - TEMPORARY SERVICE | MHASSAN | Approved | |
05/08/2019 | ELECTRIC - UNDERGROUND | MHASSAN | Approved | |
05/08/2019 | PLUMBING - YARD WTR LINE/TEST | MHASSAN | Approved | |
05/08/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
05/08/2019 | ELECTRIC - PROGRESS | MHASSAN | Approved | |
05/08/2019 | ROOF NAILING | MHASSAN | Approved | |
05/09/2019 | ELECTRIC - ABOVE CEILING | MHASSAN | Approved | |
05/09/2019 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | |
05/09/2019 | MECHANICAL - ABOVE CEILING | MHASSAN | Approved | |
05/09/2019 | TEP CLEARANCE - AM | MHASSAN | Approved | CODE ECO |
05/10/2019 | PLUMBING - ABOVE CEILING | MHASSAN | Approved | |
05/10/2019 | BUILDING ABOVE CEILING | MHASSAN | Approved | |
05/13/2019 | PLUMBING - ROOF DRAINS | RCAMACHO | Approved | |
05/24/2019 | U VALUE FOR WINDOW | MHASSAN | Approved | |
05/24/2019 | FIREWALL/FIREBARRIER/FIRESTOP | MHASSAN | Approved | |
05/28/2019 | ELECTRIC - OUTDOOR LIGHTING | MHASSAN | Approved | |
05/28/2019 | ELECTRIC - FINAL | MHASSAN | Approved | |
06/06/2019 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
06/14/2019 | OUTDOOR LIGHTING FINAL | MHASSAN | Approved | |
06/19/2019 | FIRE - FINAL | CBASALDUA | Approved | |
06/19/2019 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
08/23/2019 | CERTIFICATE OF OCCUPANCY | TVALENCIA | Approved | |
08/23/2019 | BUILDING - FINAL | TVALENCIA | Approved |