Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 05/08/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
|
| 02/13/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
18 light pole bases parking lot SE & SW see rifi 38 solid copper in Lieu of ground rods for detail 3/ES 1.03 |
| 02/12/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
|
| 02/04/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
panels 39 through 51 OK. See highlighted drawing in job trailer |
| 01/28/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
panel footings around building only OK. Finish cleaning the debris out of footings, raise electrical underground piping, and installing wall plates before pour. |
| 12/18/2018 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
Work incomplete. |
| 12/17/2018 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Interior footings. |