Permit: T18CM08149
Permit Details
Apply Date:
10/11/2018
Applicant:
Description:
3 RECHARGE BASINS, METER VAULT, PIPPING SMALLPARK
Permit Reviews
Permit Number - T18CM08149
Permit Status: Expired
Permit Description: 3 RECHARGE BASINS, METER VAULT, PIPPING SMALLPARK
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/09/2019 | RESUBMITTAL | 05/10/2019 | COMPLETED |
10/11/2018 | PLANS OK TO SUBMIT - COMM | 10/26/2018 | COMPLETED |
10/26/2018 | COMMERCIAL - NEW | 05/09/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM08149
Permit Status: Expired
Permit Description: 3 RECHARGE BASINS, METER VAULT, PIPPING SMALLPARK
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/11/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T18CM08149
Permite Description: 3 RECHARGE BASINS, METER VAULT, PIPPING SMALLPARK
Total Outstanding Inspections - 11
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/04/2022 | COT - LCBU - Stem Wall/Retaining Wall | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - LCBU - Building Final | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - LCEL - Electrical Intermediate | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - LCEL - Outdoor Lighting | N/A | Canceled | Inspection Canceled |
11/04/2022 | TRSP - ROW - Final/Close-Out | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - LCEL - Electrical Final | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - FCON - Fire - Final | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Canceled | Inspection Canceled |
11/07/2022 | COT - LCEL - Electrical Underground | N/A | Canceled | Inspection Canceled |
11/07/2022 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Canceled | Inspection Canceled |
11/07/2022 | COT - LCBU - Preslab | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T18CM08149
Permit Description: 3 RECHARGE BASINS, METER VAULT, PIPPING SMALLPARK
Total Completed Inspections - 12
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/19/2019 | COT - LCBU - Masonry Pregrout | Passed | {Activity date: 12/19/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 12/18/2019; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - second lift for uni-sex restrooms and family ok for grout.} ; {Activity date: 12/16/2019; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - First lift on Uni-sex, & Family restrooms ok for grout.} ; {Activity date: 12/12/2019; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Not ready for inspection on arrival} | |
01/07/2020 | COT - LCBU - Framing | Passed | {Activity date: 01/07/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
01/07/2020 | COT - LCBU - Exterior Clips/Sheathing | Passed | {Activity date: 01/07/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
01/07/2020 | COT - LCBU - Roof Nailing | Passed | {Activity date: 01/07/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
01/14/2020 | COT - LCPL - Yard Water Line | Passed | {Activity date: 01/14/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } ; {Activity date: 11/27/2019; Status: Partial Approval; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - Domestic water lines underground within building footprint OK } |
|
01/22/2020 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 01/22/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 01/21/2020; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Couldn’t access site due to excessive mud. } ; {Activity date: 11/25/2019; Status: Partial Approval; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - Plumbing rough at both restrooms OK} ; {Activity date: 11/21/2019; Status: Not ready for Inspection; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - Jobsite closed down due to weather} ; {Activity date: 11/20/2019; Status: Partial Approval; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - Plumbing rough soil on single restroom OK up to clean out.} |
|
02/12/2020 | COT - LCPL - Sewer | Passed | {Activity date: 02/12/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - APPROVED PER 3090 APPROVAL} ; {Activity date: 12/20/2019; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by SFLORES2 - Site Sewer Ready for Manhole installments.} ; {Activity date: 11/25/2019; Status: Partial Approval; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - Site sewer from single restroom to man hole ok to cover, still need air test.} ; {Activity date: 11/21/2019; Status: Not ready for Inspection; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - Jobsite closed down due to weather} ; {Activity date: 11/20/2019; Status: Partial Approval; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - 4 inch sewer from single restroom manhole to gang restroom manhole and on to existing ok, new man holes not installed at this time, tie in to existing not done at this time.} ; {Activity date: 11/19/2019; Status: Not ready for Inspection; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - No address posted, unable to locate job site} | |
02/12/2020 | COT - LCPL - Plumbing Final | Passed | {Activity date: 02/12/2020; Status: Approved; Inspector: WGALLAG1; Comment: Entered by DMERANZ1 - } | |
09/22/2020 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 09/22/2020; Status: Approved; Inspector: rledonne; Comment: Entered by RLEDONN1 - } | |
09/22/2020 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 09/22/2020; Status: Approved; Inspector: rledonne; Comment: Entered by RLEDONN1 - } | |
09/22/2020 | ENGR Engineering Final | Passed | {Activity date: 09/22/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Approved.} | |
09/22/2020 | PDSD Building Division - Sign Final | Passed | {Activity date: 09/22/2020; Status: Approved; Inspector: rledonne; Comment: Entered by RLEDONN1 - } |