Permit: T18CM07233
Permit Details
Apply Date:
09/12/2018
Applicant:
RICHMOND AMERICAN CONSTRUCTION INC
Description:
SFR T25BMV T17-M0055
Contractors:
- RICHMOND AMERICAN CONSTRUCTION INC
Permit Reviews
Permit Number - T18CM07233
Permit Status: Final
Permit Description: SFR T25BMV T17-M0055
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/12/2018 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 09/12/2018 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T18CM07233
Permit Status: Final
Permit Description: SFR T25BMV T17-M0055
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/12/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM07233
Permit Description: SFR T25BMV T17-M0055
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/25/2018 | PLUMBING - SEWER HCS CONNECT | TVALENC1 | Approved | IVRS - Inspection :* |
09/25/2018 | PLUMBING - YARD WTR LINE/TEST | TVALENC1 | Approved | IVRS - Inspection :* |
09/25/2018 | PLUMBING - ROUGH, SOIL | TVALENC1 | Approved | IVRS - Inspection :* |
09/28/2018 | BUILDING PRE-SLAB | BJONES | Approved | |
09/28/2018 | ELECTRIC - UNDERGROUND | BJONES | Approved | |
09/28/2018 | EXCAVATION/LAYOUT REBAR & ZON | BJONES | Approved | |
10/29/2018 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | |
10/30/2018 | ROOF NAILING | TVALENCIA | Approved | |
11/16/2018 | ELECTRIC - UFER | DMUNIZ | Approved | 1) Seal 2 car Garage front chases. 2) Block combustion and relief vents. 3) Replace damaged H2O heater B-vent. 4) Correct swaled top plates above cut studs at garage relief vents. 5) West entry top plates need fire foam. 6) Rebuild Tub diverter wall in east hall bath. 7) Move N. Kitchen counter GFCI to window stud. 8) S.E. Bedroom- staple romex out of box. 9) Fire foam N. Kitchen & S.E. bedroom top plates. 10) Secure Master BR. 4 gang switch box. 11) Move PEX from master shower can light, need 12" clearance. 12) Master BR. ABS needs FHA & stud shoe. 13) Laundry recept needs to be tied into circuit. 14) Nail off dryer FHA strap. |
11/16/2018 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | |
11/16/2018 | ELECTRIC - CABLE DROP | DMUNIZ | Approved | |
11/21/2018 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
11/27/2018 | PLUMBING - GAS PRESSURE TEST | MHASSAN | Approved | |
11/27/2018 | PLUMBING - INTERMEDIATE | MHASSAN | Approved | |
11/27/2018 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | |
11/27/2018 | FRAMING | MHASSAN | Approved | |
12/17/2018 | SHEET ROCK NAILING | DQUINN | Approved | |
12/17/2018 | BUILDING - FINAL | DQUINN | Approved | Called in due to 1045 not being on permit |
01/18/2019 | TEP CLEARANCE - AM | DMUNIZ | Approved | ECO |
02/12/2019 | PLUMBING - GAS RECONNECT | DMUNIZ | Approved | CLEAR GAS |
02/13/2019 | GAS CLEARANCE | DMUNIZ | Approved | |
02/19/2019 | MECHANICAL - FINAL | DMUNIZ | Approved | |
02/19/2019 | PLUMBING - FINAL | DMUNIZ | Approved | |
02/19/2019 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
02/19/2019 | ELECTRIC - FINAL | DMUNIZ | Approved |