Permit Details

Status:
Inspections Complete
Type:
Commercial Building
Address NEW:
3950 E IRVINGTON RD 43
Apply Date:
08/14/2018
Applicant:
Description:
NEW POWER PLANT

Permit Reviews

Permit Number - T18CM06339
Permit Status: Inspections complete
Permit Description: NEW POWER PLANT
Start Date Submittal Complete Date Status  
08/14/2018 COMMERCIAL - NEW 08/29/2018 ACTIVE Review Details
08/14/2018 PLANS OK TO SUBMIT - COMM 08/14/2018 COMPLETED Review Details
09/04/2018 RESUBMITTAL 09/13/2018 ACTIVE Review Details

Outstanding Activity Conditions

Permit Number - T18CM06339
Permit Status: Inspections complete
Permit Description: NEW POWER PLANT
Total Outstanding Activity Conditions - 1
Date Name
08/14/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: T18CM06339
Permit Description: NEW POWER PLANT
Total Completed Inspections - 15
Date Description Inspector Results Comments
01/03/2019 COT - LCEL - Electrical Underground Passed {Activity date: 01/03/2019; Status: Approved; Inspector: B Jones; Comment: Entered by BJONES1 - Conduits per plan with 16-6" and 20-1/14" PVC with Metal Risers}
01/03/2019 COT - LCEL - Grounding/Bonding Passed {Activity date: 01/03/2019; Status: Approved; Inspector: B Jones; Comment: Entered by BJONES1 - 1/2" Copper Cad Welded to Rebar}
01/24/2019 COT - LCBU - Preslab Passed {Activity date: 01/24/2019; Status: Approved; Inspector: BJONES; Comment: Entered by CBELL1 - Rebar per plan details Sheet SGMP-S-0301
8" OC EW #7 top Matt
8" OC EW #6 bottom Matt
1/2" stranded copper grounding electrodes
Cad Welded to to Rebar Matt
8 sets of bolts per plan North Side
Containment area for sump at West Side
Electrical conduits per plan North to south and East to control}
12/09/2019 TRSP - ROW - Final/Close-Out Passed {Activity date: 12/09/2019; Status: Approved; Inspector: B Mong; Comment: Entered by MBRAVIN1 - No ROW issues}
08/11/2020 COT - LCBU - Building Above Ceiling Passed {Activity date: 08/11/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved}
08/11/2020 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 08/11/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 12/09/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - complete development package noted on engineer in final for landscape final.}
08/11/2020 COT - LCBU - Building Final Passed {Activity date: 08/11/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved} ; {Activity date: 12/09/2019; Status: Not ready for Inspection; Inspector: JCLAXTON; Comment: Entered by DMERANZ1 - Need permanent labels for all panel.
Need to label all breakers.
Install required emergency lights and exit lights.
Complete mechanical.
Need engineering and fire finals.}
08/11/2020 COT - LCBU - Framing Passed {Activity date: 08/11/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved}
08/11/2020 COT - LCBU - Roof Nailing Passed {Activity date: 08/11/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved}
08/11/2020 COT - LCBU - Building Progress Passed {Activity date: 08/11/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved} ; {Activity date: 02/04/2019; Status: Partial Approval; Inspector: BJONES; Comment: Entered by CBELL1 - Hold downs bolts per spec
Footings 6-#8 top and bottom #6 8” OC South 6 #8 T&B #4 8”OC to Slab
Slab E&W #4 8”OC
1/2” grounding electrode conductors per plan
Conduits in 7 locations per plan
Installation per sheet SGMP-S0300.DGC}
08/13/2020 COT - FCON - Alarm - Final Passed {Activity date: 08/13/2020; Status: Approved; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 08/11/2020; Status: Partial Approval; Inspector: jfordney; Comment: Entered by JFORDNE1 - see t18cm05882}
08/13/2020 COT - FCON - Sprinkler - Final Passed {Activity date: 08/13/2020; Status: Approved; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 08/11/2020; Status: Partial Approval; Inspector: jfordney; Comment: Entered by JFORDNE1 - see t18cm05882}
08/13/2020 COT - FCON - Fire - Final Passed {Activity date: 08/13/2020; Status: Approved; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 08/11/2020; Status: Partial Approval; Inspector: jfordney; Comment: Entered by JFORDNE1 - see t18cm05882}
04/01/2022 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 04/01/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - PREVIOUSLY APPROVED ON 01/02/2019} ; {Activity date: 02/05/2019; Status: Partial Approval; Inspector: BJones; Comment: Entered by BJONES1 - 4'X6'Footing, Hold Down Base with bolts, Conduits, 1/2"Braided Copper Grounding Electrode Conductors 7 locations Cad Welded West 2 Matts 6 #8 Top and Bottom, with #6 at 8" OC South 6 #8 Top and Bottom. #4 to Slab Work per Sheet SGMP-S 0300. DGN} ; {Activity date: 01/22/2019; Status: Partial Approval; Inspector: bjones; Comment: Entered by BJONES1 - Rebar, Ufer with Cad Welding to steel, and Conduit per plan} ; {Activity date: 01/02/2019; Status: Approved; Inspector: BJONES; Comment: Entered by CBELL1 - #8 Rebar EW with #6 Rebar EW per page SGP-S-0305
Ufer Grounding Electrodes Conductors
1/2" stranded copper Cad Welded to Rebar
16-6" and 20 11/4" PVC Conduits per plan}
04/01/2022 ENGR Engineering Final Passed {Activity date: 04/01/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 08/11/2020; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Not ready. Complete all work and notes on development packages for this project for engineering final.} ; {Activity date: 12/09/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Development package DP17-0267. Must be complete before signing off this permit.}