Permit: T18CM06022
Permit Details
Apply Date:
08/02/2018
Applicant:
EZEQUIEL GALOTTI
Description:
TI: DEALERSHIP
Contractors:
- RYCON CONSTRUCTION INC
Permit Reviews
Permit Number - T18CM06022
Permit Status: L of c
Permit Description: TI: DEALERSHIP
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/08/2019 | RESUBMITTAL | 05/21/2019 | COMPLETED |
02/03/2020 | REVISION - - 4TH | 03/23/2020 | COMPLETED |
05/21/2019 | REVISION - - 1ST | 08/01/2019 | COMPLETED |
08/27/2019 | REVISION - - 2ND | 11/15/2019 | COMPLETED |
08/31/2018 | COMMERCIAL - TI | 10/05/2018 | COMPLETED |
10/05/2018 | RESUBMITTAL | 10/30/2018 | COMPLETED |
10/30/2018 | RESUBMITTAL | 01/08/2019 | COMPLETED |
11/07/2019 | REVISION - - 3RD | 02/03/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM06022
Permit Status: L of c
Permit Description: TI: DEALERSHIP
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/02/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM06022
Permit Description: TI: DEALERSHIP
Total Completed Inspections - 36
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/28/2019 | ELECTRIC - PROGRESS | DQUINN | Approved | Parts manager, files, warranty, and cashier rooms ok to rock and tape. |
10/28/2019 | FRAMING | DQUINN | Approved | Parts manager, files, warranty, and cashier rooms ok to rock and tape. |
11/07/2019 | PLUMBING - PRE SLAB | DQUINN | Approved | All under slab rough ok to backfill. |
11/08/2019 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | 2 double mat footings for tv columns ok to pour. |
11/08/2019 | ELECTRIC - UNDERGROUND | DQUINN | Approved | All under slab conduits for phase 1 ok to backfill and pour. |
11/15/2019 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | All phase 1 in-wall electric ok to cover. |
12/16/2019 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | All above ceiling main trunks and distribution flex ok. |
05/01/2020 | SHEET ROCK NAILING | ESTEVENS | Approved | RVI |
05/01/2020 | STUCCO MESH | ESTEVENS | Approved | RVI |
06/09/2020 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | Approved by Dan Q on 11/08/2019. |
06/09/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | Approved by Dan Q on 11/08/2019. |
06/09/2020 | PLUMBING - PROGRESS | ESTEVENS | Approved | not applicable. |
06/09/2020 | PLUMBING - ROOF DRAINS | ESTEVENS | Approved | not applicable. |
06/09/2020 | BUILDING - PROGRESS | ESTEVENS | Approved | not applicable. |
06/09/2020 | U VALUE FOR WINDOW | ESTEVENS | Approved | not applicable. |
06/09/2020 | ROOF NAILING | ESTEVENS | Approved | not applicable. |
06/09/2020 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | not applicable. |
06/09/2020 | MECHANICAL - ABOVE CEILING | ESTEVENS | Approved | |
06/09/2020 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | |
06/09/2020 | BUILDING ABOVE CEILING | ESTEVENS | Approved | |
06/16/2020 | NPPO - FINAL | BBENEDON | Approved | |
06/16/2020 | SIGN - FINAL | BBENEDON | Approved | |
06/16/2020 | LANDSCAPE - FINAL | BBENEDON | Approved | |
06/16/2020 | ENGINEERING - FINAL | BBENEDON | Approved | |
06/16/2020 | PLUMBING - ABOVE CEILING | ESTEVENS | Approved | |
06/16/2020 | PLUMBING - FINAL | ESTEVENS | Approved | |
06/16/2020 | ELECTRIC - OUTDOOR LIGHTING | ESTEVENS | Approved | |
06/16/2020 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | |
06/16/2020 | ELECTRIC - FINAL | ESTEVENS | Approved | |
06/16/2020 | MECHANICAL - PROGRESS | ESTEVENS | Approved | |
06/16/2020 | RIGHT OF WAY - FINAL | DR | Approved | Interior TI. No ROW |
06/22/2020 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
08/20/2020 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
08/25/2020 | FIRE - FINAL | jvincent | Approved | as builts submitted/approved |
08/25/2020 | FIRE - ALARM FINAL | jvincent | Approved | |
09/02/2020 | BUILDING - FINAL | ESTEVENS | Approved | All other inspections approved |