Permit Details

Status:
L of c
Type:
COMMERCIAL NEW
Address NEW:
9251 S EISENHOWER RD
Apply Date:
07/30/2018
Applicant:
DETTMER, JAMES WILLIAM - VIKING EDEBACK
Description:
WATER STORAGE AND PUMPING FACILITY
Contractors:
  • P C L CONSTRUCTION INC

Permit Reviews

Permit Number - T18CM05869
Permit Status: L of c
Permit Description: WATER STORAGE AND PUMPING FACILITY
Start Date Submittal Complete Date Status  
07/30/2018 PLANS OK TO SUBMIT - COMM 07/30/2018 COMPLETED Review Details
07/31/2018 COMMERCIAL - NEW 08/28/2018 COMPLETED Review Details
09/19/2018 COMMERCIAL - NEW 10/19/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM05869
Permit Status: L of c
Permit Description: WATER STORAGE AND PUMPING FACILITY
Total Outstanding Activity Conditions - 1
Date Name
07/30/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: L of c
Permit Number: T18CM05869
Permit Description: WATER STORAGE AND PUMPING FACILITY
Total Completed Inspections - 32
Date Description Inspector Results Comments
05/07/2019 PLUMBING - ROUGH, SOIL RCAMACHO Approved
05/16/2019 STEM WALL/RETAINING WALL RCAMACHO Approved
05/16/2019 BUILDING PRE-SLAB RCAMACHO Approved
05/16/2019 EXCAVATION/LAYOUT REBAR & ZON RCAMACHO Approved
05/29/2019 REINFORCED MASONRY PRE-GROUT MHASSAN Approved final approval is for top out of Gables and from 8 to 10 feet on interior walls.
07/01/2019 ELECTRIC - TEMPORARY SERVICE MHASSAN Approved
07/01/2019 BUILDING - PROGRESS MHASSAN Approved
07/01/2019 ROOF NAILING MHASSAN Approved submit special inspections on bolting and welding
07/08/2019 ELECTRIC - INTERMEDIATE MHASSAN Approved approval is for EWQ building
07/15/2019 FRAMING MHASSAN Approved approval was for hard lids. Please put studs back that electricians moved around.
08/20/2019 ELECTRIC - UNDERGROUND MHASSAN Approved
08/20/2019 ELECTRIC - UFER MHASSAN Approved
08/20/2019 OUTDOOR LIGHTING FINAL MHASSAN Approved lights installed unable to check functionality until TEP gets them power.
08/20/2019 ELECTRIC - OUTDOOR LIGHTING MHASSAN Approved
08/20/2019 ELECTRIC - CONSTRUCTION POWER MHASSAN Approved
08/20/2019 ELECTRIC - TEMP POWER FOR TEST MHASSAN Approved
08/20/2019 ELECTRIC - PROGRESS MHASSAN Approved
08/28/2019 SITE - SEWER MHASSAN Approved everything is covered up at this time. Underground inspections appear to be done back in May, rough soil was inspected and approved.
08/28/2019 PLUMBING - YARD WTR LINE/TEST MHASSAN Approved everything is covered up at this time. Underground inspections appear to be done back in May, rough soil was inspected and approved.
08/29/2019 MECHANICAL - INTERMEDIATE MHASSAN Approved
08/29/2019 PLUMBING - INTERMEDIATE MHASSAN Approved
08/29/2019 ELECTRIC - ABOVE CEILING MHASSAN Approved
08/30/2019 FIRE - FINAL jvincent Approved will add "electrical room" sign to door.
09/18/2019 TEP CLEARANCE - PM TVALENCIA Approved CODE ECO
12/02/2019 MECHANICAL - FINAL TVALENCIA Approved
12/02/2019 ELECTRIC - FINAL TVALENCIA Approved
12/05/2019 ENGINEERING - FINAL BBENEDON Approved
12/11/2019 BUILDING - FINAL TVALENCIA Approved APPROVED BY INSPECTOR, CLOSURE IS PENDING ALL THE SPECIAL INSPECTION CERTIFICATES AND RIGHT OF WAY INSPECTION
12/11/2019 NPPO - FINAL BBENEDON Approved
12/11/2019 SIGN - FINAL BBENEDON Approved
12/11/2019 LANDSCAPE - FINAL BBENEDON Approved
12/11/2019 PLUMBING - FINAL TVALENCIA Approved

Documents

File Name Document Type  
LETTER OF COMPLETION.PDF LETTER OF COMPLETION VIEW