Permit: T18CM05869

Parcel: 14052051C

Inspection Status: Approved

Inspection History: ELECTRIC - UNDERGROUND

Date Description Inspector Results Comments
08/20/2019 ELECTRIC - UNDERGROUND Approved
05/31/2019 ELECTRIC - UNDERGROUND Partial Approval no new work
05/30/2019 ELECTRIC - UNDERGROUND Partial Approval South duct bank to meter vault and camera 1 ok
05/17/2019 ELECTRIC - UNDERGROUND Partial Approval 2 x 1 1/2” from boosters to east side of vault complete
3 x 1 1/2” from boosters to north side of vault except risers
05/16/2019 ELECTRIC - UNDERGROUND Partial Approval 3" conduits from south duct bank to boosters only
05/03/2019 ELECTRIC - UNDERGROUND Partial Approval All conduits tied into reservoir only
04/26/2019 ELECTRIC - UNDERGROUND Partial Approval Pull box at north east corner of reservoir OK to backfill
04/25/2019 ELECTRIC - UNDERGROUND Partial Approval Conduit bank north of reservoir OK to cover
04/24/2019 ELECTRIC - UNDERGROUND Partial Approval Approximately 380 foot south duct bank to reservoir, meter vault and two cameras
04/01/2019 ELECTRIC - UNDERGROUND Partial Approval WEST DUCT BANK OK TO COVER
03/26/2019 ELECTRIC - UNDERGROUND Partial Approval From temporary job trailers to Northgate junction box With camera 4
03/21/2019 ELECTRIC - UNDERGROUND Partial Approval Main access gate junction box OK to backfill. Number three camera junction box OK to backfill.
03/15/2019 ELECTRIC - UNDERGROUND Partial Approval West duct bank from 60 foot west of Y on road to termination at chemical building
1x2" & 1x1 1/2" to pedestal
03/08/2019 ELECTRIC - UNDERGROUND Partial Approval West duct bank 60 feet west of Y to road
03/07/2019 ELECTRIC - UNDERGROUND Partial Approval West duct bank from previous to 60 foot West
03/06/2019 ELECTRIC - UNDERGROUND Partial Approval West duct bank from electrical room to 80 foot West
02/28/2019 ELECTRIC - UNDERGROUND Partial Approval 6×3 1/2 inch secondaries from transformer to control room panel
Control room and water quality room OK to slurry
01/22/2019 ELECTRIC - UNDERGROUND Not ready for Inspection Met with super preconstruction meeting