Permit: T18CM05552
Permit Details
Apply Date:
07/17/2018
Applicant:
RYAN SCHMITT - DLR GROUP
Description:
TERMINAL C
Architects:
- BEACH, RICHARD A
Contractors:
- CRANE BUILDERS INC
Permit Reviews
Permit Number - T18CM05552
Permit Status: C of o
Permit Description: TERMINAL C
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/17/2018 | COMMERCIAL - TI | 07/17/2018 | COMPLETED |
| 07/17/2018 | 3RD PARTY REVIEW - COMMERCIAL TI | 08/22/2018 | COMPLETED |
| 08/22/2018 | RESUBMITTAL | 08/24/2018 | ACTIVE |
| 08/27/2018 | POST 3RD PARTY REVIEW | 08/27/2018 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T18CM05552
Permit Status: C of o
Permit Description: TERMINAL C
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/17/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM05552
Permit Description: TERMINAL C
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/15/2018 | PLUMBING - ABOVE CEILING | RCAMACHO | Approved | |
| 10/15/2018 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | |
| 11/28/2018 | FRAMING | RCAMACHO | Approved | |
| 11/30/2018 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | |
| 12/03/2018 | MECHANICAL - ABOVE CEILING | RCAMACHO | Approved | |
| 12/07/2018 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | |
| 12/07/2018 | ELECTRIC - ABOVE CEILING | RCAMACHO | Approved | |
| 12/20/2018 | BUILDING - FINAL | RCAMACHO | Approved | air balance approved |
| 12/20/2018 | PLUMBING - PROGRESS | RCAMACHO | Approved | |
| 12/20/2018 | BUILDING - FINAL | RCAMACHO | Approved | Pending air balance report to Bob Sherry 8 AM to 9:30 AM |
| 12/20/2018 | ELECTRIC - SERVICE UPGRADE | RCAMACHO | Approved | NA |
| 12/20/2018 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | |
| 12/20/2018 | MECHANICAL - PROGRESS | RCAMACHO | Approved | |
| 12/20/2018 | BUILDING ABOVE CEILING | RCAMACHO | Approved | |
| 12/20/2018 | ELECTRIC - PROGRESS | RCAMACHO | Approved | |
| 12/20/2018 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | |
| 12/20/2018 | PLUMBING - FINAL | RCAMACHO | Approved | |
| 12/20/2018 | ELECTRIC - FINAL | RCAMACHO | Approved | |
| 12/20/2018 | ENGINEERING - FINAL | BBENEDON | Approved | |
| 12/26/2018 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 12/27/2018 | FIRE - ALARM FINAL | CBASALDUA | Approved | 1. Tested all new devices and horn/strobes. All passed. 2. Verified new devices with panel. 3. Restroom strobes changes can be verified on Fire Final. |
| 12/28/2018 | FIRE - FINAL | CBASALDUA | Approved | |
| 01/04/2019 | BUILDING PRE-SLAB | RCAMACHO | Approved | |
| 01/09/2019 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE COMPLETED |