Permit: T18CM05140
Permit Details
Apply Date:
06/29/2018
Applicant:
PEPPER VINER DEVELOPMENT CO II L L C
Description:
SFR PEPP0030 T15-M0010
Contractors:
- PEPPER VINER DEVELOPMENT CO II L L C ***APA***
Permit Reviews
Permit Number - T18CM05140
Permit Status: C of o
Permit Description: SFR PEPP0030 T15-M0010
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/29/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 06/29/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM05140
Permit Status: C of o
Permit Description: SFR PEPP0030 T15-M0010
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/29/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM05140
Permit Description: SFR PEPP0030 T15-M0010
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/16/2018 | PLUMBING - SEWER HCS CONNECT | MHASSAN | Approved | connection Point covered up at time of inspection due to overnight rain |
| 10/16/2018 | PLUMBING - YARD WTR LINE/TEST | MHASSAN | Approved | |
| 10/16/2018 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | already has been postponed once due to weather everything appears okay however unable to test for leaks due to overnight rain again and trenches are full of water. |
| 10/24/2018 | ELECTRIC - UFER | DQUINN | Approved | Need 20' of rebar in bottom third of footing. Not 17' with 3' bent verticle. Add appropriate length and attach to existing with 3 tie wires |
| 10/24/2018 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 10/25/2018 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | |
| 12/07/2018 | ROOF NAILING | RCHANDLER | Approved | |
| 12/07/2018 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | |
| 01/08/2019 | TEP CLEARANCE - AM | TVALENCIA | Approved | ECO |
| 02/05/2019 | MECHANICAL - INTERMEDIATE | TVALENCIA | Approved | |
| 02/05/2019 | PLUMBING - GAS PRESSURE TEST | TVALENCIA | Approved | |
| 02/05/2019 | ELECTRIC - INTERMEDIATE | TVALENCIA | Approved | |
| 02/05/2019 | U VALUE FOR WINDOW | TVALENCIA | Approved | |
| 02/08/2019 | PLUMBING - INTERMEDIATE | TVALENCIA | Approved | |
| 02/08/2019 | FRAMING | TVALENCIA | Approved | |
| 02/15/2019 | SHEET ROCK NAILING | ESTEVENS | Approved | |
| 04/11/2019 | GAS CLEARANCE | ESTEVENS | Approved | |
| 04/11/2019 | PLUMBING - FINAL | ESTEVENS | Approved | |
| 04/11/2019 | PLUMBING - GAS PRESS TEST FNL | ESTEVENS | Approved | Also needs a gas clearance. |
| 04/15/2019 | ELECTRIC - FINAL | RCHANDLER | Approved | |
| 04/15/2019 | MECHANICAL - FINAL | RCHANDLER | Approved | |
| 04/15/2019 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | |
| 04/15/2019 | ELECTRIC - TEMPORARY SERVICE | RCHANDLER | Approved | |
| 04/15/2019 | ELECTRIC - CABLE DROP | RCHANDLER | Approved | |
| 04/15/2019 | BUILDING - PROGRESS | RCHANDLER | Approved | |
| 04/15/2019 | STUCCO MESH | RCHANDLER | Approved | |
| 04/19/2019 | BUILDING - FINAL | RCHANDLER | Approved | paperwork received-cb |