Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
SOLAR WAIVER - COMM
Address NEW:
6200 S HEMISPHERE PL
Apply Date:
06/20/2018
Applicant:
WILSON ELECTRIC SERVICES CORP
Description:
INSTALL SHADE STRUCTURE MOUNTED SOLAR PV SYSTEM
Contractors:
  • WILSON ELECTRIC SERVICES CORP ** APA **

Permit Reviews

Permit Number - T18CM04807
Permit Status: Final
Permit Description: INSTALL SHADE STRUCTURE MOUNTED SOLAR PV SYSTEM
Start Date Submittal Complete Date Status  
06/20/2018 PLANS OK TO SUBMIT - COMM 06/21/2018 COMPLETED Review Details
06/21/2018 COMMERCIAL - BLDG/FIRE/ZONING/ENG 08/09/2018 COMPLETED Review Details
08/08/2018 RESUBMITTAL 09/04/2018 COMPLETED Review Details
09/04/2018 RESUBMITTAL 10/10/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM04807
Permit Status: Final
Permit Description: INSTALL SHADE STRUCTURE MOUNTED SOLAR PV SYSTEM
Total Outstanding Activity Conditions - 1
Date Name
06/20/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T18CM04807
Permit Description: INSTALL SHADE STRUCTURE MOUNTED SOLAR PV SYSTEM
Total Completed Inspections - 14
Date Description Inspector Results Comments
11/21/2018 ELECTRIC - UFER MHASSAN Approved array a, b, and c okay
11/26/2018 EXCAVATION/LAYOUT REBAR & ZON RCHANDLER Approved Also observed two users
12/17/2018 ROOF NAILING BJONES Approved
12/20/2018 ELECTRIC - UNDERGROUND DQUINN Approved
02/14/2019 OUTDOOR LIGHTING FINAL RCAMACHO Approved No one found on site no plans on site left a message Wilson electric
02/15/2019 ELECTRIC - OUTDOOR LIGHTING DQUINN Approved
02/15/2019 ELECTRIC - PROGRESS DQUINN Approved
02/15/2019 ELECTRIC - INTERMEDIATE DQUINN Approved
02/25/2019 TEP CLEARANCE - PM DQUINN Approved CODE DGC/DGL
02/25/2019 ELECTRIC - FINAL DQUINN Approved
02/25/2019 BUILDING - FINAL DQUINN Approved
02/25/2019 FRAMING DQUINN Approved APPROVAL UPON 1090 BY DQUINN
02/25/2019 ELECTRIC - FINAL DQUINN Approved
02/25/2019 BUILDING - FINAL DQUINN Approved