Permit: T18CM04357
Permit Details
Apply Date:
06/05/2018
Applicant:
METRO TED
Description:
TI : OFFICE
Contractors:
- W E O NEIL CONSTRUCTION CO OF ARIZONA
Permit Reviews
Permit Number - T18CM04357
Permit Status: Final
Permit Description: TI : OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/05/2018 | COMMERCIAL - TI | 06/14/2018 | COMPLETED |
06/14/2018 | RESUBMITTAL | 06/27/2018 | COMPLETED |
07/18/2018 | REVISION - - 1ST | 07/30/2018 | COMPLETED |
07/30/2018 | REVISION - - 1ST | 08/01/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM04357
Permit Status: Final
Permit Description: TI : OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/05/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM04357
Permit Description: TI : OFFICE
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/11/2018 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
07/19/2018 | BUILDING ABOVE CEILING | mramber1 | Approved | add electrical to permit |
07/20/2018 | ELECTRIC - UFER | GWest | Approved | Braided copper cable Ufer at underground conduit from transformer to future exterior switchgear. |
07/20/2018 | ELECTRIC - UNDERGROUND | GWest | Approved | Exterior conduit underground at transformer. |
07/26/2018 | PLUMBING - PROGRESS | DQUINN | Approved | OK TO SHEETROCK AND TAPE |
07/26/2018 | PLUMBING - ABOVE CEILING | DQUINN | Approved | |
07/26/2018 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
07/26/2018 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | |
07/26/2018 | FRAMING | DQUINN | Approved | |
07/26/2018 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
07/26/2018 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
10/08/2018 | ELECTRIC - CONSTRUCTION POWER | MRAMBER | Approved | |
10/15/2018 | TEP CLEARANCE - AM | MRAMBER | Approved | ECO |
01/18/2019 | ELECTRIC - SERVICE UPGRADE | RCAMACHO | Approved | approved upon 2090 approval from RCAMACHO |
01/18/2019 | ELECTRIC - TEMPORARY SERVICE | RCAMACHO | Approved | approved upon 2090 approval from RCAMACHO |
01/18/2019 | ELECTRIC - ABOVE CEILING | RCAMACHO | Approved | approved upon 2090 approval from RCAMACHO |
01/18/2019 | ELECTRIC - FINAL | RCAMACHO | Approved | |
03/28/2019 | ROOF NAILING | AKLEINSORGE | Approved | approval upon 1090 approval from AKLEINSORGE |
09/23/2021 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
09/23/2021 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
10/17/2022 | BUILDING - FINAL | CTREVIL | Approved |