Permit Details

Status:
L of c
Type:
SINGLE FAMILY ADDITION
Address:
4019 E 27TH ST
Address NEW:
4019 E 27TH ST
Apply Date:
05/15/2018
Applicant:
DONALD LIVINGSTON
Description:
ADDITION: MASTER BEDROOM & BATH

Permit Reviews

Permit Number - T18CM03773
Permit Status: L of c
Permit Description: ADDITION: MASTER BEDROOM & BATH
Start Date Submittal Complete Date Status  
05/15/2018 PLANS OK TO SUBMIT - RES 05/16/2018 COMPLETED Review Details
05/31/2018 REVISION - - 1ST 06/08/2018 COMPLETED Review Details
08/21/2018 REVISION - - 2ND 08/21/2018 ACTIVE Review Details

Outstanding Activity Conditions

Permit Number - T18CM03773
Permit Status: L of c
Permit Description: ADDITION: MASTER BEDROOM & BATH
Total Outstanding Activity Conditions - 1
Date Name
05/15/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: L of c
Permit Number: T18CM03773
Permit Description: ADDITION: MASTER BEDROOM & BATH
Total Completed Inspections - 14
Date Description Inspector Results Comments
07/10/2018 PLUMBING - ROUGH, SOIL GWest Approved
07/10/2018 BUILDING PRE-SLAB GWest Approved
07/10/2018 EXCAVATION/LAYOUT REBAR & ZON GWest Approved
08/31/2018 EXT METAL CLIPS/EXT SHEATHING GWest Approved Plan revision for Trusses to be replaced by Rafters and Ceiling joist and sizes approved by Ken.
09/11/2018 ROOF NAILING BJONES Approved framing per engineers design
11/14/2018 PLUMBING - INTERMEDIATE MHASSAN Approved
11/14/2018 ELECTRIC - INTERMEDIATE MHASSAN Approved make sure can lights maintain inch and a half clearance on sides and 3 inches above to combustibles and plastic pipes. Use correct exterior boxes that are designed to hold more than one Romex if using multiple exterior lights.
11/14/2018 FRAMING MHASSAN Approved okay to cover insulate all but ceiling in bath and closet.
03/20/2019 MECHANICAL - INTERMEDIATE RCHANDLER Approved
03/20/2019 STUCCO MESH RCHANDLER Approved
03/20/2019 MECHANICAL - FINAL RCHANDLER Approved
03/20/2019 PLUMBING - FINAL RCHANDLER Approved
03/21/2019 ELECTRIC - FINAL RCHANDLER Approved
03/21/2019 BUILDING - FINAL RCHANDLER Approved

Documents

File Name Document Type  
None LETTER OF COMPLETION VIEW
001_SITE PLAN.TIF CONSTRPLANS VIEW
002_FOUNDATION.TIF CONSTRPLANS VIEW
003_FLOOR PLAN.TIF CONSTRPLANS VIEW
004_DETAILS / ELEVATIONS / SECTIONS.TIF CONSTRPLANS VIEW
005_ROOF FRAMING.TIF CONSTRPLANS VIEW
006_PLUMBING.TIF CONSTRPLANS VIEW
007_ELECTRICAL.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW