Permit: T17CM09494
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
2920 N OLD FORT LOWELL CT
Address NEW:
2920 N OLD FORT LOWELL CT
Apply Date:
12/27/2017
Applicant:
TIMOTHY ROBERTSON
Description:
NEW SFR
Permit Reviews
Permit Number - T17CM09494
Permit Status: Final
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/09/2018 | RESIDENTIAL - BLDG/ZONING/ENGINE/WWM | 02/08/2018 | COMPLETED |
| 02/08/2018 | RESUBMITTAL | 03/02/2018 | COMPLETED |
| 03/08/2018 | REVISION - - 1ST | 03/08/2018 | COMPLETED |
| 12/27/2017 | PLANS OK TO SUBMIT - RES | 12/27/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM09494
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/27/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM09494
Permit Description: NEW SFR
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/26/2018 | REINFORCED MASONRY PRE-GROUT | MHASSAN1 | Approved | FINISH VERTICALS ON N WALL, S3.2 DTAIL 20 &21 CHECK REBAR TO MATCH BOND BEAM, ANY VERTICALS THAT DON'T PENETRATE THE BOND BEAM TIE ONE NEXT TO IT KEEPING THE MINIMUM LAP PER #5 BAR |
| 04/30/2018 | BUILDING PRE-SLAB | DFLORES2 | Approved | |
| 05/25/2018 | PLUMBING - SEWER HCS CONNECT | TVALENC1 | Approved | IVRS - Inspection :* |
| 05/29/2018 | EXCAVATION/LAYOUT REBAR & ZON | BJONES | Approved | |
| 06/01/2018 | PLUMBING - ROUGH, SOIL | TVALENC1 | Approved | IVRS - Inspection :* |
| 06/14/2018 | STEM WALL/RETAINING WALL | DFLORES2 | Approved | OK TO PROCEED WITH STEM WALL |
| 07/13/2018 | ROOF NAILING | TVALENC1 | Approved | IVRS - Inspection :* |
| 07/13/2018 | EXT METAL CLIPS/EXT SHEATHING | TVALENC1 | Approved | IVRS - Inspection :* |
| 07/16/2018 | ELECTRIC - UNDERGROUND | DFLORES2 | Approved | |
| 09/07/2018 | PLUMBING - YARD WTR LINE/TEST | DFLORES2 | Approved | IVRS - Inspection :* |
| 09/07/2018 | PLUMBING - INTERMEDIATE | DFLORES2 | Approved | IVRS - Inspection :* |
| 09/07/2018 | ELECTRIC - CONSTRUCTION POWER | DFLORES2 | Approved | IVRS - Inspection :* |
| 09/07/2018 | ELECTRIC - INTERMEDIATE | DFLORES2 | Approved | IVRS - Inspection :* |
| 09/07/2018 | ELECTRIC - UFER | DFLORES2 | Approved | IVRS - Inspection :* |
| 09/07/2018 | U VALUE FOR WINDOW | DFLORES2 | Approved | IVRS - Inspection :* |
| 09/07/2018 | STUCCO MESH | DFLORES2 | Approved | IVRS - Inspection :* |
| 09/07/2018 | FRAMING | DFLORES2 | Approved | IVRS - Inspection :* |
| 09/10/2018 | TEP CLEARANCE - AM | DFLORES | Approved | ECO |
| 09/12/2018 | MECHANICAL - INTERMEDIATE | DFLORES2 | Approved | |
| 10/26/2018 | SHEET ROCK NAILING | DQUINN | Approved | |
| 03/07/2019 | FIRE SPKLR - FINAL | gsereno1 | Approved | |
| 03/08/2019 | MECHANICAL - FINAL | RCHANDLER | Approved | |
| 03/08/2019 | PLUMBING - FINAL | RCHANDLER | Approved | |
| 03/08/2019 | PLUMBING - PROGRESS | RCHANDLER | Approved | |
| 03/08/2019 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | |
| 03/08/2019 | ELECTRIC - FINAL | RCHANDLER | Approved | |
| 03/08/2019 | BUILDING - FINAL | RCHANDLER | Approved |