Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM07765
Permit Details
Apply Date:
10/16/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW DATA CENTER
Architects:
- CAJERO, NICK FERNANDEZ
Contractors:
- BRASFIELD AND GORRIE L L C , *** APA ***
Permit Reviews
Permit Number - T17CM07765
Permit Status: C of o
Permit Description: NEW DATA CENTER
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/06/2018 | REVISION - - 1ST | 04/11/2018 | COMPLETED |
10/16/2017 | PLANS OK TO SUBMIT - COMM | 10/17/2017 | COMPLETED |
10/17/2017 | COMMERCIAL - NEW | 11/13/2017 | COMPLETED |
11/13/2017 | RESUBMITTAL | 11/27/2017 | COMPLETED |
11/27/2017 | RESUBMITTAL | 02/09/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM07765
Permit Status: C of o
Permit Description: NEW DATA CENTER
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/16/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM07765
Permit Description: NEW DATA CENTER
Total Completed Inspections - 39
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/30/2018 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | AFTER HOURS APA ACCOUNT $165.00 |
08/02/2018 | PLUMBING - YARD WTR LINE/TEST | RCAMACHO | Approved | 200 LB TEST OK |
08/02/2018 | PLUMBING - YARD WTR LINE/TEST | RCAMACH1 | Approved | IVRS - Inspection :* |
09/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | PEDESTRUAN BRIDGE FOOTERS WEST OF DATA CENTER |
09/07/2018 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | |
10/11/2018 | FRAMING | RCAMACHO | Approved | |
10/17/2018 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | 100 pound test on domestic water up to back flow |
11/16/2018 | ELECTRIC - ABOVE CEILING | RCAMACHO | Approved | |
11/16/2018 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | |
11/20/2018 | ELECTRIC - TEMPORARY SERVICE | RCAMACHO | Approved | Panels HA9, HA9A, 3PDT-1A,H/C9AEM, H/C9BEM T/A 9A, T/C9BEM,ATSEM disconnect CU1 & Air jandler 1 AHU1 OK TO ENERGIZE FOR TEST TO REMAIN LOCKED OUT AND TAGGED OUT |
11/27/2018 | ELECTRIC - PROGRESS | RCAMACHO | Approved | Pre final inspection only |
11/28/2018 | PLUMBING - GAS PRESS TEST FNL | RCAMACHO | Approved | per Rick Baldwin |
11/28/2018 | PLUMBING - PROGRESS | RCAMACHO | Approved | |
11/28/2018 | BUILDING - PROGRESS | RCAMACHO | Approved | |
11/28/2018 | BUILDING PRE-SLAB | RCAMACHO | Approved | |
11/29/2018 | FIRE - FINAL | JPEELDAVIS | Approved | OK FOR TCO Need to complete some small items: Test the emergency and primary power once it is installed Need to check a few items on the fire alarm sytsem Need to have the duct fire smoke detectors installed in the HVAC units Need to have the building address installed Need to order the FDC and Control Valve signs Fire sprinkler is 99% approved minus needing to replace one painted head. Fire alarm system needs to have the candella rating confirmed. Priamry power confirmed and a few other small items. |
11/29/2018 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | |
11/29/2018 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | |
11/29/2018 | ELECTRIC - UFER | MRAMBER | Approved | TA-9ups, TD-9, LD-9 ok to energize |
11/30/2018 | BUILDING - FINAL | MRAMBER | Approved | Ok to apply for T.C.O. C.L. 1 thru 6 |
11/30/2018 | MECHANICAL - FINAL | MRAMBER | Approved | Ok to apply for T.C.O. C.L. 1 thru 6 |
11/30/2018 | MECHANICAL - PROGRESS | MRAMBER | Approved | |
11/30/2018 | PLUMBING - FINAL | MRAMBER | Approved | Ok to apply for T.C O. C.L. 1 thru 6 |
11/30/2018 | PLUMBING - ROOF DRAINS | MRAMBER | Approved | |
11/30/2018 | PLUMBING - PRE SLAB | MRAMBER | Approved | |
11/30/2018 | ELECTRIC - FINAL | MRAMBER | Approved | Ok to apply for T.C.O. C.L. 1 thru 6. |
12/04/2018 | ENGINEERING - FINAL | BBENEDON | Approved | Inspector has no issues preventing |
12/05/2018 | PLUMBING - ABOVE CEILING | RCAMACHO | Approved | |
12/05/2018 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | |
12/07/2018 | SITE - SEWER | RCAMACHO | Approved | Not ready for inspection no work |
12/07/2018 | PLUMBING - BACK WATER VALVE | RCAMACHO | Approved | Not ready for inspection no work |
12/07/2018 | MECHANICAL - ABOVE CEILING | RCAMACHO | Approved | |
12/07/2018 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | |
12/07/2018 | MECHANICAL - UNDERGROUND | RCAMACHO | Approved | |
01/08/2019 | ELECTRIC - OUTDOOR LIGHTING | RCAMACHO | Approved | |
02/14/2019 | OUTDOOR LIGHTING FINAL | RCAMACHO | Approved | |
02/28/2019 | TEP CLEARANCE - PM | RCAMACHO | Approved | CODE ECO |
08/27/2019 | ELECTRIC - SERVICE UPGRADE | MHASSAN | Approved | not applicable |
08/27/2019 | CERTIFICATE OF OCCUPANCY | MHASSAN | Approved |