Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
10/03/2017
Applicant:
KIM WILFORTH
Description:
HOSPITAL
Architects:
  • BEACH, RICHARD A
Contractors:
  • HENSEL PHELPS CONSTRUCTION CO

Permit Reviews

Permit Number - T17CM07498
Permit Status: C of o
Permit Description: HOSPITAL
Start Date Submittal Complete Date Status  
03/22/2018 3RD PARTY REVIEW - REVISION/OTHER 03/23/2018 COMPLETED Review Details
10/03/2017 PLANS OK TO SUBMIT - COMM 10/03/2017 COMPLETED Review Details
10/03/2017 3RD PARTY REVIEW - COMMERCIAL 12/12/2017 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM07498
Permit Status: C of o
Permit Description: HOSPITAL
Total Outstanding Activity Conditions - 1
Date Name
10/03/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T17CM07498
Permit Description: HOSPITAL
Total Completed Inspections - 24
Date Description Inspector Results Comments
06/14/2018 FIRE - FINAL JPEELDAVIS Approved L3 Phase 3 approved
06/14/2018 FIRE - ALARM FINAL JPEELDAVIS Approved L3 Phase 3 approved
06/14/2018 FIRE SPKLR - FINAL JPEELDAVIS Approved L3 Phase 3 approved
06/15/2018 ELECTRIC - SERVICE UPGRADE JBURGE Approved
06/15/2018 MECHANICAL - FINAL JBURGE Approved
06/15/2018 MECHANICAL - PROGRESS JBURGE Approved
06/15/2018 MECHANICAL - ABOVE CEILING JBURGE Approved
06/15/2018 MECHANICAL - INTERMEDIATE JBURGE Approved
06/15/2018 PLUMBING - PROGRESS JBURGE Approved
06/15/2018 PLUMBING - ABOVE CEILING JBURGE Approved
06/15/2018 PLUMBING - INTERMEDIATE JBURGE Approved
06/15/2018 ELECTRIC - FINAL JBURGE Approved
06/15/2018 ELECTRIC - PROGRESS JBURGE Approved
06/15/2018 ELECTRIC - ABOVE CEILING JBURGE Approved
06/15/2018 ELECTRIC - INTERMEDIATE JBURGE Approved
06/15/2018 BUILDING - PROGRESS JBURGE Approved
06/15/2018 BUILDING ABOVE CEILING JBURGE Approved
06/22/2018 ENGINEERING - FINAL JBURGE Approved OK FOR TCO
06/22/2018 PLUMBING - FINAL JBURGE Approved
06/22/2018 BUILDING - FINAL JBURGE Approved
04/11/2019 NPPO - FINAL BBENEDON Approved
04/11/2019 SIGN - FINAL BBENEDON Approved
04/11/2019 LANDSCAPE - FINAL BBENEDON Approved
04/11/2019 RIGHT OF WAY - FINAL DR Approved

Documents

File Name Document Type  
None CERT OF OCC VIEW