Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 06/15/2018 |
BUILDING - PROGRESS |
|
Approved |
|
| 06/05/2018 |
BUILDING - PROGRESS |
|
Partial Approval |
PRE-TEMOROARY CERTIFICATE OF OCCUPANCY MEETING. |
| 05/04/2018 |
BUILDING - PROGRESS |
|
Partial Approval |
SHEET ROCK NAILING - LEVEL #1, EAST MRI ROOM. OK TO TAPE. |
| 04/24/2018 |
BUILDING - PROGRESS |
|
Partial Approval |
SHEET ROCK NAILING: LEVEL 3 WEST AT GL: C-G/4-6. OK TO TAPE PROGRESS AREAS. |
| 04/19/2018 |
BUILDING - PROGRESS |
|
Partial Approval |
LEVEL #3 - EAST; PLUMBING ABOVE CEILING - BLENDED CHILLED WATER LINES AT 3/4" - 4": LINES TESTED AT 100 PSI. |
| 04/18/2018 |
BUILDING - PROGRESS |
|
Partial Approval |
SHEET ROCK NAILING: LEVEL #3, WEST: ROOMS AND CORRIDORS AT GL: D.5/2-4.7; 2/D.5-F.3 . OK TO TAPE PROGRESS AREA. FRAMING: LEVEL #1: MRI ROOM AT APPROXIMATELY D/19; PROTECTICE SHEETING IN PLACE. OK TO SHEET ROCK. |
| 03/23/2018 |
BUILDING - PROGRESS |
|
Partial Approval |
LEVEL #3, WEST SIDE; IN-WALL ELECTRIC. |
| 03/20/2018 |
BUILDING - PROGRESS |
|
Partial Approval |
SHEET ROCK NAILING AT LEVEL #3 - EAST: INTERIOR ROOMS AND HALLWAYS. OK TO TAPE PROGRESS AREAS. |
| 03/19/2018 |
BUILDING - PROGRESS |
|
Not ready for Inspection |
CONTRACTOR CANCELLED: SHEET ROCK NAILING |
| 02/22/2018 |
BUILDING - PROGRESS |
|
Partial Approval |
WALL FRAMING: LEVEL #3, WEST - WALL FRAMING AT GL: C-G/2 -8. |
| 02/21/2018 |
BUILDING - PROGRESS |
|
Partial Approval |
FRAMING ON LEVEL #3, AREA "C": GL: D - H/15 - 18. |