Permit: T17CM06789
Permit Details
Apply Date:
09/05/2017
Applicant:
MESIK, JOEL DAVID
Description:
FOUNDATION ONLY FOR NEW CATERPILLAR SM&T HQ
Architects:
- MESIK, JOEL DAVID
Contractors:
- SUNDT CORP ,
Permit Reviews
Permit Number - T17CM06789
Permit Status: Final
Permit Description: FOUNDATION ONLY FOR NEW CATERPILLAR SM&T HQ
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/05/2017 | PLANS OK TO SUBMIT - COMM | 09/06/2017 | COMPLETED |
09/11/2017 | COMMERCIAL - NEW | 11/09/2017 | COMPLETED |
11/09/2017 | RESUBMITTAL | 11/17/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM06789
Permit Status: Final
Permit Description: FOUNDATION ONLY FOR NEW CATERPILLAR SM&T HQ
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/05/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM06789
Permit Description: FOUNDATION ONLY FOR NEW CATERPILLAR SM&T HQ
Total Completed Inspections - 4
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | LINE B OK TO POUR TOPS TO BOLTS |
12/17/2019 | REINFORCED MASONRY PRE-GROUT | ESTEVENS | Approved | No access to site. Called contact number left a message. Arrived 10:00. |
01/08/2020 | BUILDING PRE-SLAB | aquiroz | Approved | |
01/08/2020 | STEM WALL/RETAINING WALL | aquiroz | Approved |