Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address:
3025 S KINO PW
Address NEW:
3025 S KINO PW
Apply Date:
06/21/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
RETAIL
Architects:
  • PAWAR, DEVENDRA P
Contractors:
  • STEVE JULIUS CONSTRUCTION INC

Permit Reviews

Permit Number - T17CM04810
Permit Status: C of o
Permit Description: RETAIL
Start Date Submittal Complete Date Status  
02/07/2018 REVISION - - 1ST 02/07/2018 COMPLETED Review Details
02/07/2018 REVISION - - 1ST 02/21/2018 COMPLETED Review Details
06/21/2017 PLANS OK TO SUBMIT - COMM 06/21/2017 COMPLETED Review Details
06/21/2017 COMMERCIAL - NEW 08/03/2017 COMPLETED Review Details
08/03/2017 RESUBMITTAL 08/11/2017 COMPLETED Review Details
08/11/2017 RESUBMITTAL 10/30/2017 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM04810
Permit Status: C of o
Permit Description: RETAIL
Total Outstanding Activity Conditions - 1
Date Name
06/21/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T17CM04810
Permit Description: RETAIL
Total Completed Inspections - 37
Date Description Inspector Results Comments
12/05/2017 SITE - SEWER mramber1 Approved site sewer from footer (sitewall) to property line to grease receptor tie in ok to back fill
12/08/2017 ELECTRIC - UNDERGROUND mramber1 Approved within bldg footprint
12/08/2017 PLUMBING - ROUGH, SOIL mramber1 Approved within bldg footprint
12/13/2017 ELECTRIC - UFER mramber1 Approved
12/13/2017 EXCAVATION/LAYOUT REBAR & ZON mramber1 Approved bldg ok except trench drains and turn downs
12/19/2017 PLUMBING - YARD WTR LINE/TEST mramber1 Approved ok thru CMU stem wall only
12/22/2017 FIRE SPKLR - UG, PIPING, HYDRO jvincent Approved
12/22/2017 BUILDING PRE-SLAB mramber1 Approved service bay area and tire storage area ok
12/22/2017 REINFORCED MASONRY PRE-GROUT mramber1 Approved no work
12/27/2017 FIRE SPKLR - UG PIPING FLUSH jvincent Approved
03/09/2018 FRAMING mramber1 Approved densglas ok on exterior
03/12/2018 PLUMBING - ABOVE CEILING BJones Approved
03/12/2018 ELECTRIC - ABOVE CEILING BJones Approved
03/14/2018 PLUMBING - PROGRESS mramber1 Approved
03/14/2018 PLUMBING - SEWER HCS CONNECT mramber1 Approved
03/29/2018 BUILDING - PROGRESS BJones Approved
04/02/2018 TEP CLEARANCE - AM BJONES Approved RECN
04/02/2018 ELECTRIC - PROGRESS BJones Approved OK to Set Electrical Meter
04/30/2018 BUILDING ABOVE CEILING BBENEDO1 Approved IVRS - Inspection :*
04/30/2018 MECHANICAL - ABOVE CEILING BBENEDO1 Approved IVRS - Inspection :*
05/07/2018 MECHANICAL - INTERMEDIATE BBENEDO1 Approved IVRS - Inspection :*
05/08/2018 FIRE - ALARM FINAL CBASALDUA Approved
05/08/2018 FIRE SPKLR - FINAL CBASALDUA Approved
05/09/2018 ELECTRIC - INTERMEDIATE mramber1 Approved
05/11/2018 ELECTRIC - OUTDOOR LIGHTING mramber1 Approved
05/11/2018 PLUMBING - ROOF DRAINS mramber1 Approved
05/14/2018 ELECTRIC - TEMPORARY SERVICE mramber1 Approved
05/14/2018 ELECTRIC - CONSTRUCTION POWER mramber1 Approved
05/14/2018 OUTDOOR LIGHTING FINAL mramber1 Approved
05/14/2018 PLUMBING - INTERMEDIATE mramber1 Approved
05/16/2018 ENGINEERING - FINAL RLODONE Approved
05/16/2018 FIRE - FINAL gsereno1 Approved
05/16/2018 ELECTRIC - FINAL mramber1 Approved
05/16/2018 PLUMBING - FINAL mramber1 Approved
05/16/2018 MECHANICAL - FINAL mramber1 Approved
05/17/2018 CERTIFICATE OF OCCUPANCY LPEREZ Approved ALL INSPECTIONS AND SPECIAL INSPECTIONS APPROVED/ RELATED IS IN FINAL STATUS AND INSPECTIONS ON DP APPROVED FINALED
05/17/2018 BUILDING - FINAL MRAMBER Approved