Permit: T17CM03784
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
3510 N CRAYCROFT RD BLDG#8
Address NEW:
3510 N CRAYCROFT RD BLDG#8
Apply Date:
05/12/2017
Applicant:
N/A
Description:
NEW REC BLDG FOR APARTMENT COMPLEX
Architects:
- ACORN, KIM BRIAN
Contractors:
- CW BUILDERS LLC
Permit Reviews
Permit Number - T17CM03784
Permit Status: C of o
Permit Description: NEW REC BLDG FOR APARTMENT COMPLEX
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/08/2018 | REVISION - - 1ST | 04/13/2018 | COMPLETED |
| 04/29/2019 | REVISION - - 4TH | 05/03/2019 | COMPLETED |
| 05/02/2018 | REVISION - - 2ND | 05/02/2018 | COMPLETED |
| 05/02/2018 | REVISION - - 2ND | 05/30/2018 | COMPLETED |
| 05/12/2017 | PLANS OK TO SUBMIT - COMM | 05/12/2017 | COMPLETED |
| 05/12/2017 | COMMERCIAL - NEW | 06/23/2017 | COMPLETED |
| 06/23/2017 | RESUBMITTAL | 08/02/2017 | COMPLETED |
| 07/11/2018 | REVISION - - 3RD | 07/11/2018 | COMPLETED |
| 07/11/2018 | REVISION - - 3RD | 08/01/2018 | COMPLETED |
| 08/01/2018 | REVISION - - 3RD | 08/22/2018 | COMPLETED |
| 08/02/2017 | RESUBMITTAL | 08/30/2017 | COMPLETED |
| 08/30/2017 | RESUBMITTAL | 03/08/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM03784
Permit Status: C of o
Permit Description: NEW REC BLDG FOR APARTMENT COMPLEX
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/12/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM03784
Permit Description: NEW REC BLDG FOR APARTMENT COMPLEX
Total Completed Inspections - 45
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/27/2018 | PLUMBING - ROUGH, SOIL | TVALENC1 | Approved | IVRS - Inspection :* 1- ALL CORRECTIONS HAVE BEEN MADE. 2- NOTE; THIS INSPECTION IS FOR THE FIRST FLOOR UNDERGROUNG PLUMBING ONLY. OKAY TOT COVER. |
| 08/24/2018 | EXCAVATION/LAYOUT REBAR & ZON | DFLORES | Approved | |
| 09/28/2018 | PLUMBING - YARD WTR LINE/TEST | GWest | Approved | |
| 10/01/2018 | STEM WALL/RETAINING WALL | DQUINN | Approved | CHAIR LIFT AND STAIRS AND MONOLITHE WALLS OK TO GROUT |
| 10/03/2018 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 10/03/2018 | ELECTRIC - UFER | DQUINN | Approved | |
| 10/03/2018 | PLUMBING - PRE SLAB | DQUINN | Approved | |
| 10/22/2018 | ROOF NAILING | DQUINN | Approved | East office roofs OK to dry in. South lower roof ok to dry in |
| 11/15/2018 | FRAMING | DMCCARTHY | Approved | OK TO INSULATE AND DRYWALL ABOVE 9 FT TO ROOF FRAME. |
| 11/29/2018 | BUILDING - PROGRESS | GWEST | Approved | |
| 12/05/2018 | MECHANICAL - INTERMEDIATE | GWEST | Approved | |
| 12/05/2018 | ELECTRIC - INTERMEDIATE | GWEST | Approved | |
| 12/14/2018 | ELECTRIC - UNDERGROUND | GWEST | Approved | Location Pool area Bridge |
| 12/14/2018 | ELECTRIC - PROGRESS | GWEST | Approved | Location Pool area Bridge |
| 12/14/2018 | ELECTRIC - PROGRESS | GWEST | Approved | Location Pool area Bridge |
| 12/20/2018 | SHEET ROCK NAILING | GWEST | Approved | Second layer (Not the Drop) |
| 01/04/2019 | PLUMBING - ROOF DRAINS | GWEST | Approved | roof drain systems |
| 01/04/2019 | PLUMBING - INTERMEDIATE | GWEST | Approved | roof drain systems |
| 01/08/2019 | PLUMBING - GAS PRESS TEST FNL | GWEST | Approved | |
| 01/10/2019 | SITE - SEWER | GWEST | Approved | |
| 01/15/2019 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | |
| 01/24/2019 | POOL/SPA GAS | DQUINN | Approved | |
| 01/24/2019 | MECHANICAL - HOODS | DQUINN | Approved | |
| 01/24/2019 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | |
| 01/24/2019 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | |
| 01/24/2019 | U VALUE FOR WINDOW | DQUINN | Approved | |
| 01/24/2019 | BUILDING ABOVE CEILING | DQUINN | Approved | |
| 01/25/2019 | GAS CLEARANCE | DQUINN | Approved | |
| 01/28/2019 | STUCCO MESH | GWEST | Approved | |
| 03/20/2019 | TEP CLEARANCE - PM | RCHANDLER | Approved | CODE ECO |
| 04/22/2019 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 04/22/2019 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 04/23/2019 | ELECTRIC - SERVICE UPGRADE | GWEST | Approved | approved upon 2090 approval |
| 04/23/2019 | MECHANICAL - FINAL | GWEST | Approved | |
| 04/23/2019 | MECHANICAL - PROGRESS | GWEST | Approved | approved upon 4090 approval |
| 04/23/2019 | PLUMBING - FINAL | GWEST | Approved | |
| 04/23/2019 | PLUMBING - PROGRESS | GWEST | Approved | approved upon 3090 approval |
| 04/23/2019 | PLUMBING - ABOVE CEILING | GWEST | Approved | approved upon 3090 approval |
| 04/23/2019 | ELECTRIC - FINAL | GWEST | Approved | |
| 04/23/2019 | ELECTRIC - OUTDOOR LIGHTING | GWEST | Approved | approved upon 2090 approval |
| 04/23/2019 | ELECTRIC - CONSTRUCTION POWER | GWEST | Approved | approved upon 2090 approval |
| 07/03/2019 | FIRE - FINAL | gsereno1 | Approved | Locking caps will be installed when all buildings are approved. |
| 07/10/2019 | BUILDING - FINAL | CTREVI | Approved | |
| 07/10/2019 | RIGHT OF WAY - FINAL | CTREVI | Approved | |
| 07/10/2019 | ENGINEERING - FINAL | CTREVI | Approved |