Permit: T17CM01475
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
2 E CONGRESS ST 05
Address NEW:
2 E CONGRESS ST 05
Apply Date:
02/23/2017
Applicant:
ROBERT CAYLOR CONSTRUCTION COMPANY
Description:
APARTMENTS 5TH FLOOR
Contractors:
- ROBERT CAYLOR CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T17CM01475
Permit Status: C of o
Permit Description: APARTMENTS 5TH FLOOR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/23/2017 | PLANS OK TO SUBMIT - COMM | 02/28/2017 | COMPLETED |
| 02/28/2017 | COMMERCIAL - TI | 03/20/2017 | COMPLETED |
| 03/27/2017 | RESUBMITTAL - TI ALL | 04/18/2017 | COMPLETED |
| 04/18/2017 | RESUBMITTAL | 04/18/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM01475
Permit Status: C of o
Permit Description: APARTMENTS 5TH FLOOR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/23/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM01475
Permit Description: APARTMENTS 5TH FLOOR
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/28/2017 | NPPO - FINAL | DROBERTS | Approved | |
| 04/28/2017 | SIGN - FINAL | DROBERTS | Approved | |
| 04/28/2017 | LANDSCAPE - FINAL | DROBERTS | Approved | |
| 04/28/2017 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 05/01/2017 | RIGHT OF WAY - FINAL | DR | Approved | |
| 06/19/2017 | ELECTRIC - SERVICE UPGRADE | mramber1 | Approved | |
| 06/20/2017 | TEP CLEARANCE - AM | MRAMBER | Approved | INCR TO CLEAR ALL UNITS 501 THRU 507 |
| 06/22/2017 | FRAMING | mramber1 | Approved | |
| 06/22/2017 | BUILDING ABOVE CEILING | mramber1 | Approved | |
| 06/22/2017 | SHEET ROCK NAILING | mramber1 | Approved | |
| 06/22/2017 | ELECTRIC - INTERMEDIATE | mramber1 | Approved | |
| 06/22/2017 | ELECTRIC - ABOVE CEILING | mramber1 | Approved | |
| 06/22/2017 | ELECTRIC - PROGRESS | mramber1 | Approved | |
| 06/22/2017 | PLUMBING - INTERMEDIATE | mramber1 | Approved | |
| 06/22/2017 | PLUMBING - ABOVE CEILING | mramber1 | Approved | |
| 06/22/2017 | MECHANICAL - INTERMEDIATE | mramber1 | Approved | |
| 06/22/2017 | MECHANICAL - PROGRESS | mramber1 | Approved | |
| 06/22/2017 | MECHANICAL - ABOVE CEILING | mramber1 | Approved | |
| 06/28/2017 | PLUMBING - PROGRESS | mramber1 | Approved | W/C flanges ok |
| 07/27/2017 | ELECTRIC - FINAL | mramber1 | Approved | |
| 07/27/2017 | PLUMBING - GAS PRESS TEST FNL | mramber1 | Approved | |
| 07/27/2017 | PLUMBING - FINAL | mramber1 | Approved | |
| 07/27/2017 | BUILDING - PROGRESS | mramber1 | Approved | |
| 10/05/2017 | FIRE - FINAL | GDAURIA | Approved | |
| 10/05/2017 | MECHANICAL - FINAL | AQUIROZ | Approved | |
| 10/05/2017 | BUILDING - FINAL | AQUIROZ | Approved |