Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/22/2017 | PLUMBING - INTERMEDIATE | Approved | ||
| 05/03/2017 | PLUMBING - INTERMEDIATE | Partial Approval | 503 thru 509 ok walls only | |
| 04/28/2017 | PLUMBING - INTERMEDIATE | Partial Approval | HALLWAY ONLY | |
| 04/26/2017 | PLUMBING - INTERMEDIATE | Partial Approval | 5TH FLOOR UNITS #501 AND 502 ONLY PROVIDE LETTER FROM ENGINEER ON RECORD DOMESTIC WATER PIPING TO BE TYPE L COPPER PER APPROVED PLAN NOTE 4. CHANGED TO CVPC INSTALLED PROCEED AT OWN RISK. |
|
| 04/25/2017 | PLUMBING - INTERMEDIATE | Not ready for Inspection | PRE CON MEETING |