Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM01297
Permit Details
Apply Date:
02/16/2017
Applicant:
CATALANO, VINCENT VICTOR
Description:
NEW SHELL BLDG
Architects:
- CATALANO, VINCENT VICTOR
Contractors:
- MONZURES COMPANY LLC
Permit Reviews
Permit Number - T17CM01297
Permit Status: L of c
Permit Description: NEW SHELL BLDG
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/16/2017 | PLANS OK TO SUBMIT - COMM | 02/17/2017 | COMPLETED |
02/21/2017 | COMMERCIAL - NEW | 03/21/2017 | COMPLETED |
03/24/2017 | RESUBMITTAL | 04/11/2017 | COMPLETED |
04/11/2017 | RESUBMITTAL | 04/17/2017 | COMPLETED |
04/19/2017 | REVISION - - 1ST | 04/19/2017 | COMPLETED |
06/12/2017 | REVISION - - 2ND | 06/12/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM01297
Permit Status: L of c
Permit Description: NEW SHELL BLDG
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/16/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T17CM01297
Permit Description: NEW SHELL BLDG
Total Completed Inspections - 34
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/08/2017 | PLUMBING - YARD WTR LINE/TEST | NORTH | Approved | |
05/08/2017 | PLUMBING - SEWER HCS CONNECT | NORTH | Approved | |
05/19/2017 | BUILDING PRE-SLAB | MPUGH1 | Approved | IVRS - Inspection :* |
05/19/2017 | EXCAVATION/LAYOUT REBAR & ZON | MPUGH1 | Approved | IVRS - Inspection :* |
08/07/2017 | ROOF NAILING | JMILITE1 | Approved | |
08/09/2017 | EXT METAL CLIPS/EXT SHEATHING | MPUGH1 | Approved | IVRS - Inspection :* |
08/17/2017 | FRAMING | MPUGH1 | Approved | IVRS - Inspection :* |
08/18/2017 | ELECTRIC - INTERMEDIATE | mpugh1 | Approved | |
08/25/2017 | STUCCO MESH | bbenedon | Approved | |
08/29/2017 | PLUMBING - ROOF DRAINS | MPUGH1 | Approved | IVRS - Inspection :* |
09/05/2017 | MECHANICAL - INTERMEDIATE | MPUGH1 | Approved | IVRS - Inspection :* |
09/06/2017 | SHEET ROCK NAILING | MPUGH1 | Approved | IVRS - Inspection :* |
09/21/2017 | U VALUE FOR WINDOW | MPUGH1 | Approved | IVRS - Inspection :* |
09/26/2017 | ELECTRIC - CONSTRUCTION POWER | NORTH | Approved | |
09/27/2017 | TEP CLEARANCE - AM | NORTH | Approved | ECO |
11/13/2017 | FIRE - FINAL | CBASALDUA | Approved | |
11/13/2017 | FIRE SPKLR - FINAL | CBASALDUA | Approved | Shell sprinklers |
11/14/2017 | PLUMBING - INTERMEDIATE | RGREEN | Approved | |
11/14/2017 | SITE - SEWER | RGREEN | Approved | |
11/14/2017 | BUILDING ABOVE CEILING | RGREEN | Approved | |
11/14/2017 | ELECTRIC - PROGRESS | RGREEN | Approved | |
11/14/2017 | ELECTRIC - TEMPORARY SERVICE | RGREEN | Approved | |
11/14/2017 | BUILDING - PROGRESS | RGREEN | Approved | |
11/14/2017 | MECHANICAL - FINAL | RGREENE1 | Approved | |
11/14/2017 | PLUMBING - FINAL | RGREENE1 | Approved | |
11/14/2017 | BUILDING - FINAL | RGREENE1 | Approved | |
11/14/2017 | ELECTRIC - OUTDOOR LIGHTING | RGREENE1 | Approved | |
11/14/2017 | OUTDOOR LIGHTING FINAL | RGREENE1 | Approved | |
11/14/2017 | ELECTRIC - ABOVE CEILING | RGREENE1 | Approved | |
11/14/2017 | ELECTRIC - UNDERGROUND | RGREENE1 | Approved | |
11/14/2017 | ELECTRIC - UFER | RGREENE1 | Approved | |
11/14/2017 | ELECTRIC - FINAL | RGREENE1 | Approved | |
11/16/2017 | FIRE - ALARM FINAL | jvincent | Approved | |
11/28/2017 | ENGINEERING - FINAL | MRUSSO | Approved |