Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 11/14/2017 |
BUILDING - PROGRESS |
|
Approved |
|
| 10/26/2017 |
BUILDING - PROGRESS |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 08/18/2017 |
BUILDING - PROGRESS |
|
Partial Approval |
north unit sewer line ok, keep joints exposed. |
| 08/01/2017 |
BUILDING - PROGRESS |
|
Partial Approval |
ok to complete sheating |
| 07/19/2017 |
BUILDING - PROGRESS |
|
Partial Approval |
ok to start sheathing |
| 06/05/2017 |
BUILDING - PROGRESS |
|
Partial Approval |
stem ok to pour |
| 06/01/2017 |
BUILDING - PROGRESS |
|
Not ready for Inspection |
IVRS - Inspection :* complete vertical steel @ H.D.' |
| 05/26/2017 |
BUILDING - PROGRESS |
|
Partial Approval |
trash enclosure footings ok |
| 05/25/2017 |
BUILDING - PROGRESS |
|
Partial Approval |
retaining wall footing ok |