Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM00167
Permit Details
Status:
C of o
Type:
COMMERCIAL ADDITION
Address:
2797 N CERRADA DE BETO
Address NEW:
2797 N CERRADA DE BETO
Apply Date:
01/09/2017
Applicant:
JOEL KRAMER INDEVCO
Description:
ASSISTED LIVING ADULT CARE
Architects:
- DINGLE, KORY ALLEN
Contractors:
- INDEVCO CONSTRUCTION INC
Permit Reviews
Permit Number - T17CM00167
Permit Status: C of o
Permit Description: ASSISTED LIVING ADULT CARE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/09/2017 | PLANS OK TO SUBMIT - COMM | 01/09/2017 | COMPLETED |
| 01/09/2017 | 3RD PARTY REVIEW - COMMERCIAL TI | 05/03/2017 | COMPLETED |
| 05/18/2017 | POST 3RD PARTY REVIEW | 05/19/2017 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T17CM00167
Permit Status: C of o
Permit Description: ASSISTED LIVING ADULT CARE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/09/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM00167
Permit Description: ASSISTED LIVING ADULT CARE
Total Completed Inspections - 37
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/15/2017 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | EAST SIDE SECTION OF PROJECT ONLY |
| 05/18/2018 | PLUMBING - ROOF DRAINS | bbenedo1 | Approved | |
| 05/18/2018 | SITE - SEWER | bbenedo1 | Approved | |
| 05/18/2018 | ELECTRIC - CABLE DROP | bbenedo1 | Approved | |
| 05/18/2018 | ROOF NAILING | bbenedo1 | Approved | |
| 05/18/2018 | BUILDING PRE-SLAB | bbenedo1 | Approved | |
| 05/24/2018 | SHEET ROCK NAILING | BSTEVENS | Approved | |
| 08/23/2018 | PLUMBING - GAS PRESSURE TEST | ESTEVEN1 | Approved | APPROVED |
| 10/09/2018 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | |
| 10/09/2018 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | |
| 10/09/2018 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | |
| 10/09/2018 | STUCCO MESH | ESTEVENS | Approved | |
| 10/09/2018 | FRAMING | ESTEVENS | Approved | |
| 10/09/2018 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | |
| 10/09/2018 | U VALUE FOR WINDOW | ESTEVENS | Approved | |
| 11/08/2018 | BUILDING ABOVE CEILING | ESTEVEN1 | Approved | |
| 11/08/2018 | MECHANICAL - ABOVE CEILING | ESTEVENS | Approved | |
| 11/08/2018 | PLUMBING - ABOVE CEILING | ESTEVENS | Approved | |
| 11/08/2018 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | |
| 11/13/2018 | MECHANICAL - HOOD SYSTEMS | BSTEVENS | Approved | EXISTING HOOD WITH NEW ANSUL SYSTEM |
| 11/13/2018 | MECHANICAL - HOODS | BSTEVENS | Approved | EXISTING HOOD WITH NEW ANSUL SYSTEM |
| 11/14/2018 | PLUMBING - GAS PRESS TEST FNL | ESTEVENS | Approved | |
| 11/15/2018 | GAS CLEARANCE | ESTEVENS | Approved | |
| 11/27/2018 | FIRE - FINAL | CBASALDUA | Approved | 1. Ok for TCO to apply for State Licensing. 2. Still need to test Fire Sprinkler, Fire Alarm, and Fire Kitchen Hood System prior to occupying with residents. |
| 11/27/2018 | RIGHT OF WAY - FINAL | DR | Approved | |
| 12/04/2018 | MECHANICAL - FINAL | ESTEVENS | Approved | Pending air balance report |
| 12/04/2018 | PLUMBING - FINAL | ESTEVENS | Approved | Pending water report |
| 12/04/2018 | BUILDING - FINAL | ESTEVENS | Approved | Pending other inspections |
| 12/04/2018 | ELECTRIC - FINAL | ESTEVENS | Approved | |
| 12/05/2018 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 12/05/2018 | FIRE - KITCHEN EXH HOOD FINAL | CBASALDUA | Approved | |
| 12/31/2018 | ENGINEERING - FINAL | BBENEDON | Approved | Okay for final approval with receipt and approval of Engineers letter for final grade. |
| 01/03/2019 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 01/03/2019 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
| 01/03/2019 | NPPO - FINAL | BBENEDON | Approved | |
| 01/03/2019 | SIGN - FINAL | BBENEDON | Approved | |
| 01/03/2019 | LANDSCAPE - FINAL | BBENEDON | Approved |