Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 04/27/2018 |
PLUMBING - ROUGH, SOIL |
|
Approved |
GREASE TRAP HOLDS WATER AND HAS A CERT STAMP, OK TO BACK FILL |
| 04/12/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
KITCHEN, ALL EXCEPT FOR GREASE TRAP |
| 03/07/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
PHASE 3 COMPLETE. |
| 03/02/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
AREAS CIRCLED IN GREEN WITH INITIALS WEN |
| 02/09/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
PHASE 1 IS COMPLETE, PHASE 2 ALL EXCEPT FOR THE KITCHEN AREA |
| 01/25/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
NORTH WEST SIDE SECTION COMPLETE |
| 01/11/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
NORTH SECTION, ALL PLUMBING ON EAST SIDE OF MAIN SEWER LINE PLUS SOUTH BATH ON WEST ON MAIN |
| 01/05/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
TIE IN AT TRUNK LINE OK TO COVER |
| 01/04/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
7 STUB OUTS-OK |
| 12/15/2017 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
EAST SIDE SECTION OF PROJECT ONLY |