Permit: T17CM00140
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
9250 S HOUGHTON RD
Address NEW:
9250 S HOUGHTON RD
Apply Date:
01/06/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
RETAIL
Contractors:
- RYAN COMPANIES U S INC
Permit Reviews
Permit Number - T17CM00140
Permit Status: C of o
Permit Description: RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/06/2017 | PLANS OK TO SUBMIT - COMM | 01/06/2017 | COMPLETED |
| 01/06/2017 | COMMERCIAL - TI | 03/09/2017 | COMPLETED |
| 03/09/2017 | RESUBMITTAL - TI ALL | 03/30/2017 | COMPLETED |
| 03/30/2017 | RESUBMITTAL - TI ALL | 07/19/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM00140
Permit Status: C of o
Permit Description: RETAIL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/06/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM00140
Permit Description: RETAIL
Total Completed Inspections - 31
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/17/2017 | PLUMBING - ROUGH, SOIL | bbenedon | Approved | |
| 05/02/2017 | FRAMING | DQUINN | Approved | PETCO OK TO INSULATE |
| 05/10/2017 | MECHANICAL - INTERMEDIATE | bbenedon | Approved | |
| 05/22/2017 | ELECTRIC - INTERMEDIATE | bbenedon | Approved | |
| 05/22/2017 | PLUMBING - INTERMEDIATE | bbenedon | Approved | |
| 06/12/2017 | PLUMBING - YARD WTR LINE/TEST | bbenedon | Approved | |
| 06/12/2017 | ELECTRIC - UFER | bbenedon | Approved | |
| 06/12/2017 | ELECTRIC - UNDERGROUND | bbenedon | Approved | |
| 06/12/2017 | SHEET ROCK NAILING | bbenedon | Approved | |
| 06/13/2017 | ELECTRIC - ABOVE CEILING | bbenedon | Approved | |
| 06/16/2017 | ELECTRIC - PROGRESS | benedon | Approved | ECO |
| 06/16/2017 | ELECTRIC - OUTDOOR LIGHTING | benedon | Approved | |
| 06/16/2017 | ELECTRIC - CONSTRUCTION POWER | benedon | Approved | |
| 06/19/2017 | TEP CLEARANCE - AM | BBENEDON | Approved | ECO |
| 06/20/2017 | PLUMBING - GAS PRESSURE TEST | bbenedon | Approved | |
| 06/21/2017 | GAS CLEARANCE | BBENDEON | Approved | |
| 06/27/2017 | MECHANICAL - ABOVE CEILING | bbenedon | Approved | |
| 06/27/2017 | PLUMBING - ABOVE CEILING | bbenedon | Approved | |
| 06/27/2017 | BUILDING - PROGRESS | bbenedon | Approved | |
| 06/30/2017 | PLUMBING - PROGRESS | Bbenedon | Approved | |
| 06/30/2017 | BUILDING ABOVE CEILING | Bbenedon | Approved | |
| 07/21/2017 | PLUMBING - FINAL | bbenedon | Approved | |
| 07/21/2017 | OUTDOOR LIGHTING FINAL | bbenedon | Approved | |
| 07/21/2017 | ELECTRIC - FINAL | bbenedon | Approved | |
| 07/26/2017 | FIRE - FINAL | jvincent | Approved | -Address numbers on order. Will mount to top of bldg N. side. |
| 07/26/2017 | FIRE - ALARM FINAL | jvincent | Approved | |
| 07/26/2017 | FIRE SPKLR - FINAL | jvincent | Approved | |
| 07/26/2017 | ENGINEERING - FINAL | MRUSSO | Approved | SITE WORK HAS BEEN COMPLETED |
| 07/28/2017 | BUILDING - FINAL | BBENEDON | Approved | Fire and Engineering APPROVED Air Balance REPORT SENT TO RECORDS |
| 07/28/2017 | CERTIFICATE OF OCCUPANCY | BBENEDON | Approved | Fire and Engineering APPROVED Air Balance REPORT SENT TO RECORDS |
| 07/28/2017 | MECHANICAL - FINAL | BBENEDON | Approved | Air Balance REPORT SENT TO RECORDS |