Permit: T16CM07762
Permit Details
Apply Date:
10/11/2016
Applicant:
CDG ARCHITECTS
Description:
NEW OFFICE BUILDING
Contractors:
- B F L CONSTRUCTION CO INC ,
Permit Reviews
Permit Number - T16CM07762
Permit Status: C of o
Permit Description: NEW OFFICE BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/16/2017 | REVISION - - 1ST | 03/23/2017 | COMPLETED |
| 10/11/2016 | PLANS OK TO SUBMIT - COMM | 10/13/2016 | COMPLETED |
| 10/13/2016 | COMMERCIAL - NEW | 11/18/2016 | COMPLETED |
| 12/09/2016 | RESUBMITTAL - TI ALL | 12/12/2016 | COMPLETED |
| 12/12/2016 | RESUBMITTAL - TI ALL | 12/19/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM07762
Permit Status: C of o
Permit Description: NEW OFFICE BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/11/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM07762
Permit Description: NEW OFFICE BUILDING
Total Completed Inspections - 38
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/23/2017 | SITE - SEWER | TVALENC1 | Approved | IVRS - Inspection :* |
| 02/06/2017 | ELECTRIC - TEMPORARY SERVICE | TVALENC1 | Approved | |
| 02/24/2017 | BUILDING PRE-SLAB | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/24/2017 | ELECTRIC - CONSTRUCTION POWER | JMILITE1 | Approved | SEPERATE GROUNDS AND NEUTRALS IN SUBPANEL. |
| 04/14/2017 | ELECTRIC - UNDERGROUND | TVALENC1 | Approved | |
| 04/26/2017 | PLUMBING - YARD WTR LINE/TEST | JMILITE1 | Approved | OK TO BACKFILL WATER LINE. |
| 06/14/2017 | PLUMBING - ROUGH, SOIL | TVALENC1 | Approved | 1- DWV WATER TEST PROVIDED FOR THE FLOOR SINK LOCATED IN THE BREAK ROOM #116. |
| 06/26/2017 | ELECTRIC - UFER | TVALENC1 | Approved | CLEAR ELECTRIC ECO |
| 06/26/2017 | ELECTRIC - FINAL | TVALENC1 | Approved | CLEAR ELECTRIC ECO |
| 06/27/2017 | TEP CLEARANCE - AM | TVALENCIA | Approved | ECO |
| 07/20/2017 | MECHANICAL - ABOVE CEILING | TVALENC1 | Approved | |
| 07/20/2017 | SHEET ROCK NAILING | TVALENC1 | Approved | |
| 07/20/2017 | STUCCO MESH | TVALENC1 | Approved | |
| 09/05/2017 | BUILDING - FINAL | TVALENC1 | Approved | BLDG FINAL OKAY FOR C OF O PER TVALENCIA. |
| 09/05/2017 | EXCAVATION/LAYOUT REBAR & ZON | TVALENC1 | Approved | |
| 09/05/2017 | STEM WALL/RETAINING WALL | TVALENC1 | Approved | |
| 09/05/2017 | FRAMING | TVALENC1 | Approved | |
| 09/05/2017 | ROOF NAILING | TVALENC1 | Approved | |
| 09/05/2017 | MECHANICAL - FINAL | TVALENC1 | Approved | |
| 09/05/2017 | MECHANICAL - INTERMEDIATE | TVALENC1 | Approved | |
| 09/05/2017 | PLUMBING - FINAL | TVALENC1 | Approved | |
| 09/05/2017 | PLUMBING - PROGRESS | TVALENC1 | Approved | |
| 09/05/2017 | PLUMBING - ABOVE CEILING | TVALENC1 | Approved | |
| 09/05/2017 | PLUMBING - INTERMEDIATE | TVALENC1 | Approved | |
| 09/05/2017 | OUTDOOR LIGHTING FINAL | TVALENC1 | Approved | |
| 09/05/2017 | ELECTRIC - OUTDOOR LIGHTING | TVALENC1 | Approved | |
| 09/05/2017 | ELECTRIC - PROGRESS | TVALENC1 | Approved | |
| 09/05/2017 | ELECTRIC - ABOVE CEILING | TVALENC1 | Approved | |
| 09/05/2017 | ELECTRIC - INTERMEDIATE | TVALENC1 | Approved | |
| 09/05/2017 | BUILDING - PROGRESS | TVALENC1 | Approved | |
| 09/05/2017 | U VALUE FOR WINDOW | TVALENC1 | Approved | |
| 09/05/2017 | BUILDING ABOVE CEILING | TVALENC1 | Approved | |
| 09/05/2017 | EXT METAL CLIPS/EXT SHEATHING | TVALENC1 | Approved | |
| 09/08/2017 | FIRE - ALARM FINAL | jvincent | Approved | |
| 09/08/2017 | FIRE SPKLR - FINAL | jvincent | Approved | |
| 09/12/2017 | FIRE - FINAL | CBASALDUA | Approved | |
| 09/29/2017 | CERTIFICATE OF OCCUPANCY | TVALENCIA | Approved | |
| 09/29/2017 | ENGINEERING - FINAL | MRUSSO | Approved |