Permit: T16CM06555
Permit Details
Apply Date:
08/24/2016
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: RESTAURANT
Architects:
- FRIES, MICHAEL THOMAS
Contractors:
- RELIANCE COMMERCIAL CONSTRUCTION
Permit Reviews
Permit Number - T16CM06555
Permit Status: C of o
Permit Description: TI: RESTAURANT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/24/2016 | PLANS OK TO SUBMIT - COMM | 08/24/2016 | COMPLETED |
08/24/2016 | 3RD PARTY REVIEW - COMMERCIAL TI | 09/28/2016 | COMPLETED |
09/28/2016 | RESUBMITTAL | 10/07/2016 | COMPLETED |
12/07/2016 | 3RD PARTY REVIEW - REVISION/OTHER | 12/22/2016 | COMPLETED |
12/22/2016 | REVISION - - 1ST | 12/23/2016 | COMPLETED |
12/23/2016 | 3RD PARTY REVIEW - REVISION/OTHER | 12/29/2016 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM06555
Permit Description: TI: RESTAURANT
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/02/2016 | MECHANICAL - HOOD SYSTEMS | ESTEVEN1 | Approved | EXISITING HOOD MEETS TYPE 2 HOOD REQUIREMENTS. HOOD MUST BE APPROVED BY MECHANICAL ENGINEER FOR USE. |
12/26/2016 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | ALL INTERIOR ROUGH SOIL EXCEPT FOR GREASE INTEREPTOR. OK TO COVER PROGRESS AREAS. |
12/29/2016 | ELECTRIC - INTERMEDIATE | IVR USER | Approved | IVRS - RI canceled |
01/03/2017 | ELECTRIC - UNDERGROUND | ESTEVEN1 | Approved | APPROVED |
01/03/2017 | BUILDING PRE-SLAB | ESTEVEN1 | Approved | APPROVED |
02/10/2017 | MECHANICAL - ABOVE CEILING | BSTEVENS | Approved | |
02/10/2017 | MECHANICAL - INTERMEDIATE | BSTEVENS | Approved | |
02/10/2017 | PLUMBING - ABOVE CEILING | BSTEVENS | Approved | |
02/10/2017 | PLUMBING - INTERMEDIATE | BSTEVENS | Approved | |
02/10/2017 | ELECTRIC - ABOVE CEILING | BSTEVENS | Approved | |
02/10/2017 | FRAMING | BSTEVENS | Approved | |
02/21/2017 | SHEET ROCK NAILING | JBURGE | Approved | |
03/15/2017 | BUILDING ABOVE CEILING | RCAMACHO | Approved | IVRS - Inspection :* |
06/20/2017 | PLUMBING - GAS PRESSURE TEST | BSTEVENS | Approved | |
06/21/2017 | GAS CLEARANCE | BSTEVENS | Approved | |
08/08/2017 | MECHANICAL - HOODS | BSTEVENS | Approved | |
08/08/2017 | PLUMBING - GAS PRESS TEST FNL | BSTEVENS | Approved | |
08/08/2017 | ELECTRIC - FINAL | BSTEVENS | Approved | |
08/09/2017 | RIGHT OF WAY - FINAL | DR | Approved | |
08/09/2017 | LANDSCAPE - FINAL | MRUSSO | Approved | |
08/09/2017 | SIGN - FINAL | MRUSSO | Approved | |
08/09/2017 | NPPO - FINAL | MRUSSO | Approved | |
08/09/2017 | ENGINEERING - FINAL | MRUSSO | Approved | |
08/17/2017 | FIRE SPKLR - UG PIPING FLUSH | jdonovan | Approved | |
08/17/2017 | FIRE SPKLR - OH PIPING & HYDRO | jdonovan | Approved | |
08/17/2017 | FIRE SPKLR - UG, PIPING, HYDRO | jdonovan | Approved | |
08/17/2017 | FIRE - FINAL | jdonovan | Approved | |
08/17/2017 | FIRE SPKLR - FINAL | jdonovan | Approved | |
08/17/2017 | FIRE - ALARM FINAL | jdonovan | Approved | |
08/17/2017 | FIRE - KITCHEN EXH HOOD FINAL | jdonovan | Approved | |
08/18/2017 | BUILDING - FINAL | BSTEVENS | Approved | |
08/18/2017 | PLUMBING - FINAL | BSTEVENS | Approved | |
08/18/2017 | MECHANICAL - FINAL | BSTEVENS | Approved |