Permit: T16CM03369
Permit Details
Apply Date:
05/05/2016
Applicant:
SAYLER-BROWN, THOMAS
Description:
STORAGE
Architects:
- SAYLER-BROWN, THOMAS
Contractors:
- BUILDING EXCELLENCE L L C
Permit Reviews
Permit Number - T16CM03369
Permit Status: C of o
Permit Description: STORAGE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/05/2016 | COMMERCIAL - TI | 05/10/2016 | COMPLETED |
| 05/10/2016 | COMMERCIAL - TI | 06/22/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM03369
Permit Status: C of o
Permit Description: STORAGE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/05/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM03369
Permit Description: STORAGE
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/05/2016 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 07/14/2016 | ELECTRIC - INTERMEDIATE | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 07/14/2016 | FRAMING | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 07/18/2016 | PLUMBING - INTERMEDIATE | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 07/21/2016 | SHEET ROCK NAILING | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 07/22/2016 | BUILDING PRE-SLAB | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 08/10/2016 | MECHANICAL - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 08/10/2016 | ELECTRIC - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 08/10/2016 | BUILDING ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 08/24/2016 | PLUMBING - ABOVE CEILING | MRAMBER | Approved | |
| 08/24/2016 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 08/24/2016 | PLUMBING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 08/24/2016 | PLUMBING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 08/24/2016 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 08/24/2016 | ELECTRIC - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 08/24/2016 | ELECTRIC - OUTDOOR LIGHTING | MRAMBER | Approved | IVRS - Inspection :* |
| 08/24/2016 | ELECTRIC - OUTDOOR LIGHTING | MRAMBER | Approved | IVRS - Inspection :* |
| 08/24/2016 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 08/24/2016 | FIRE - FINAL | jvincent | Approved | |
| 12/21/2016 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 01/13/2017 | BUILDING - PROGRESS | MRAMBER | Approved |